🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Completed queue projects in West (non-ISO utilities) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown96364.7 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

963 requests · page 3 of 20
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 20-082, Washington County
Battery storage
200 MWOperating Washington, ORWest May 2020target 2023
Solar project 763, Iron County
Solar · Appaloosa Solar I, LLC
200 MWOperating Iron, UTWest Jun 2016target 2023
Solar project 567, Ada County
Solar · Pleasant Valley Solar, LLC
200 MWOperating Ada, IDWest Sep 20192025
Onshore wind project GI-TC-2021-06, Logan County
Onshore wind
200 MWOperating Logan, COWest Mar 20212021
Solar + storage project Company GU, Washoe County
Solar + storage
200 MWOperating Washoe, NVWest Sep 2015target 2021
Pebble Springs Wind Project
Onshore wind · Avangrid Power, LLC
200 MWOperating Gilliam, ORWest Jun 2002target 2004
Onshore wind project 835, Carbon County
Onshore wind · PacifiCorp
190 MWOperating Carbon, WYWest Dec 2016target 2024
Solar + storage project Q23, Maricopa County
Solar + storage
183 MWOperating Maricopa, AZWest Jun 20162023
Solar + storage project ANPP HVS-Q23
Solar + storage
183 MWOperating West Jun 2016target 2023
Gas project CSU-2020-2
Gas
178 MWOperating West Jul 20202023
Gas project IA-PNM-2012-01, Valencia County
Gas
173 MWOperating Valencia, NMWest Jul 2012
Onshore wind project GI-0717, Holt County
Onshore wind · Grande Prairie Wind
166 MWOperating Holt, NEWest Aug 2007target 2016
Gas project 97, Elmore County
Gas
162 MWOperating Elmore, IDWest Oct 2003target 2005
Onshore wind project SP107, Coconino County
Onshore wind
161 MWOperating Coconino, AZWest Jun 2023target 2024
Other project Q196, Coconino County
Other
161 MWOperating Coconino, AZWest May 2011target 2021
Goose Prairie Solar
Solar + storage · Goose Prairie Solar LLC
160 MWOperating Yakima, WAWest Nov 2017target 2022
Solar + storage project 341, Beaverhead County
Solar + storage
160 MWOperating Beaverhead, MTWest Jun 20182020
Gas project IA-PNM-2007-12
Gas
158 MWOperating NMWest Oct 2007
Onshore wind project 255, Bingham County
Onshore wind · Cedar Creek Wind, LLC
152 MWOperating Bingham, IDWest Dec 2008target 2023
Lower Snake Phase 1
Onshore wind
150 MWOperating Garfield, WAWest Aug 2007target 2011
Onshore wind project CLPT G8, Laramie County
Onshore wind · Roundhouse Interconnect, LLC
150 MWOperating Laramie, WYWest Dec 2016target 2023
Hopkins Ridge Wind
Onshore wind
150 MWOperating Columbia, WAWest May 2002target 2003
Battery storage project 657, Ada County
Battery storage · Kuna BESS LLC
150 MWOperating Ada, IDWest May 20222025
Solar project Q30, Maricopa County
Solar
150 MWOperating Maricopa, AZWest Jul 2021target 2023
Solar project Q276, Maricopa County
Solar
150 MWOperating Maricopa, AZWest Mar 2018target 2022
Solar project CLPT G14, Laramie County
Solar · South Cheyenne Solar, LLC
150 MWOperating Laramie, WYWest May 2021target 2023
Onshore wind project GI-1410, Williams County
Onshore wind · Lindahl Wind
150 MWOperating Williams, NDWest Jun 2014target 2014
Onshore wind project TI-08-0204, Kit Carson County
Onshore wind
150 MWOperating Kit Carson, COWest Feb 20082015
Solar project ANPP HVS-Q15
Solar
150 MWOperating West Jul 2010target 2019
Windtricity Ventures LLC
Onshore wind · Windtricity Ventures
150 MWOperating Klickitat, WAWest Apr 2004target 2007
Solar project ANPP HVS-Q30
Solar
150 MWOperating West Jul 2021target 2023
Solar project Company 138, Clark County
Solar
150 MWOperating Clark, NVWest Sep 2014target 2023
Onshore wind project CLPT G11, Laramie County
Onshore wind · NextEra Energy Resources Interconnection Holdings, LLC
150 MWOperating Laramie, WYWest Jun 2017target 2023
Onshore wind project GI-1414, Stark County
Onshore wind · Brady Wind
150 MWOperating Stark, NDWest Oct 2014target 2015
Solar project Q21, Maricopa County
Solar
150 MWOperating Maricopa, AZWest Jan 20162021
Solar project ANPP HVS-Q21
Solar
150 MWOperating West Jan 2016target 2021
Solar project Q30b
Solar
150 MWOperating West Jul 20212023
Onshore wind project 12, Uinta County
Onshore wind · FPL Energy Wyoming, LLC
146 MWOperating Uinta, WYWest Aug 2001target 2003
Onshore wind project TI-18-0827, Weld County
Onshore wind
145 MWOperating Weld, COWest Aug 20182022
Onshore wind project 49, Adams County
Onshore wind
144 MWOperating Adams, WAWest Nov 2016target 2020
Gas project IA-PNM-2001-12
Gas
143 MWOperating NMWest
Solar project Company 119, Clark County
Solar
140 MWOperating Clark, NVWest Sep 2013target 2022
Sky Ranch Solar / Sky Ranch Energy Storage
Solar + storage
140 MWOperating Sandoval, NMWest Sep 2017target 2022
Gas project GI-0215, Cass County
Gas
140 MWOperating Cass, IAWest Jul 2002
Onshore wind project 46, Lewis County
Onshore wind
137 MWOperating Lewis, WAWest Jan 20162019
Onshore wind project 4, Wheatland County
Onshore wind
135 MWOperating Wheatland, MTWest Apr 20012006
Onshore wind project 165, Bon Homme County
Onshore wind
130 MWOperating Bon Homme, SDWest Oct 20132014
Onshore wind project 119-A, Carbon County
Onshore wind · GreenWing Pacific Energy Corp.
128 MWOperating Carbon, WYWest Jan 2007target 2009
Solar project Q22, Maricopa County
Solar
125 MWOperating Maricopa, AZWest Feb 2016target 2025
Windy Point 1 Wind
Onshore wind · Cannon Power Corporation
125 MWOperating Klickitat, WAWest Jan 2004target 2009
Page 3 of 20

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)