Solar project Company 138, Clark County

Solar project Company 138, Clark County is a 150 MW solar request built and operating in the West interconnection queue, in Clark County, Nevada, connecting to NV Energy.

Queue statusOperating
  1. PlanningQueued Sep 2014 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget May 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Company 138
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Clark County, Nevada
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
25 September 2014
Proposed online date
May 2023

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem