🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arizona

SOLAR · WEST

Solar project Q276, Maricopa County

Solar project Q276, Maricopa County is a 150 MW solar request built and operating in the West interconnection queue, in Maricopa County, Arizona, connecting to Arizona Public Service.

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Apr 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q276
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Delaney 500kV SY
Location
Maricopa County, Arizona
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
In-Service
Queue status
Operational
Entered queue
30 March 2018
Proposed online date
April 2022

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Maricopa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem