SOLAR + STORAGE · WEST

Solar + storage project ANPP HVS-Q23

Solar + storage project ANPP HVS-Q23 is a 183 MW solar + storage request built and operating in the West interconnection queue, connecting to Salt River Project.

Queue statusOperating
  1. PlanningQueued Jun 2016 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Sep 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
ANPP HVS-Q23
Grid region
West (non-ISO utilities)
Utility / transmission owner
Salt River Project
Connection point (POI)
Hassayampa 500 kV
Technology
Solar: 183 MW · Battery
Total requested
183 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
14 June 2016
Proposed online date
September 2023

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in · Transmission lines in

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem