| Project | Capacity | Status |
|---|---|---|
| Gas project 216, Payette County Gas |
650 MW | Withdrawn / abandoned |
| Battery storage project G0961, Umatilla County Battery storage |
650 MW | Withdrawn / abandoned |
| Gas project 212, Ada County Gas |
650 MW | Withdrawn / abandoned |
| Gas project 218, Elmore County Gas |
650 MW | Withdrawn / abandoned |
| Gas project 93, Pasco County Gas · Masked |
650 MW | Withdrawn / abandoned |
| Battery storage project G1049, Harney County Battery storage |
650 MW | Withdrawn / abandoned |
| Gas project J4111, Hot Spring County Gas |
650 MW | Withdrawn / abandoned |
| Gas project G219, Johnson County Gas |
650 MW | Withdrawn / abandoned |
| Gas project 247, Payette County Gas |
650 MW | Withdrawn / abandoned |
| Gas project 243, Gem County Gas |
650 MW | Withdrawn / abandoned |
| South Bay Replacement - Option 1 Gas |
650 MW | Withdrawn / abandoned |
| Solar + storage project Q445, Maricopa County Solar + storage |
647 MW | Withdrawn / abandoned |
| Gas project F05, Armstrong County Gas |
646 MW | Withdrawn / abandoned |
| CPV St. Charles Gas |
645 MW | Withdrawn / abandoned |
| Gas project G095, Wayne County Gas |
644 MW | Withdrawn / abandoned |
| Ventus Renewable Energy Center Other |
643 MW | Withdrawn / abandoned |
| Solar + storage project Q80, Apache County Solar + storage |
643 MW | Withdrawn / abandoned |
| Gas project LGE-GIS-2007-004, Henderson County Gas |
642 MW | Withdrawn / abandoned |
| Coal project J237, Henderson County Coal |
642 MW | Withdrawn / abandoned |
| SR Bertron - CCGT Gas · NRG Energy, Inc |
641 MW | Withdrawn / abandoned |
| Solar project G0649, Wasco County Solar |
641 MW | Withdrawn / abandoned |
| Gas project IC-089, Covington County Gas |
640 MW | Withdrawn / abandoned |
| Solar + storage project Q77, Millard County Solar + storage · Intermountain Power Agency |
640 MW | Withdrawn / abandoned |
| Other project 91, Dickson County Other |
640 MW | Withdrawn / abandoned |
| Gas project GEN-2001-005, Curry County Gas |
640 MW | Withdrawn / abandoned |
| Other project 92, Union County Other |
640 MW | Withdrawn / abandoned |
| Onshore wind project GI-2016-27, Elbert County Onshore wind |
640 MW | Withdrawn / abandoned |
| Duke Energy NA Gas · Duke Energy North America, LLC |
640 MW | Withdrawn / abandoned |
| Other project 90, Maury County Other |
640 MW | Withdrawn / abandoned |
| Other project 132, Metcalfe County Other |
640 MW | Withdrawn / abandoned |
| Gas project GEN-2001-010, Leavenworth County Gas |
640 MW | Withdrawn / abandoned |
| Gas project GEN-2001-002, Johnson County Gas |
640 MW | Withdrawn / abandoned |
| Gas project IC-088, Dale County Gas |
640 MW | Withdrawn / abandoned |
| Gas project O04, Camden County Gas |
640 MW | Withdrawn / abandoned |
| Other project 85, Haywood County Other |
640 MW | Withdrawn / abandoned |
| Gas project U2-048, Burlington County Gas |
640 MW | Withdrawn / abandoned |
| Gas project IC-085, Escambia County Gas |
640 MW | Withdrawn / abandoned |
| Gas project IC-087, Tift County Gas |
640 MW | Withdrawn / abandoned |
| Gas project IC-1219, Hart County Gas |
640 MW | Withdrawn / abandoned |
| Gas project GEN-2001-009, Leavenworth County Gas |
640 MW | Withdrawn / abandoned |
| Blythe III (Revised) Gas |
640 MW | Withdrawn / abandoned |
| Gas project IC-072, Mitchell County Gas |
640 MW | Withdrawn / abandoned |
| Other project 133, Marshall County Other |
640 MW | Withdrawn / abandoned |
| Other project 124, Mccracken County Other |
640 MW | Withdrawn / abandoned |
| Solar + storage project C4-026, Harney County Solar + storage |
640 MW | Withdrawn / abandoned |
| Gas project 17, Polk County Gas · Duke Energy Florida, LLC |
640 MW | Withdrawn / abandoned |
| Gas project LGE-GIS-2007-003, Henderson County Gas |
640 MW | Withdrawn / abandoned |
| Gas project IC-1218, Lee County Gas |
640 MW | Withdrawn / abandoned |
| Gas project E17_W29, Westmoreland County Gas |
640 MW | Withdrawn / abandoned |
| Gas project IC-008, Autauga County Gas |
640 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)