🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 26

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 26 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 216, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Dec 2007target 2012
Battery storage project G0961, Umatilla County
Battery storage
650 MWWithdrawn / abandoned Umatilla, ORWest Oct 2023target 2028
Gas project 212, Ada County
Gas
650 MWWithdrawn / abandoned Ada, IDWest Dec 2007target 2012
Gas project 218, Elmore County
Gas
650 MWWithdrawn / abandoned Elmore, IDWest Dec 2007target 2012
Gas project 93, Pasco County
Gas · Masked
650 MWWithdrawn / abandoned Pasco, FLSoutheast Aug 2008target 2013
Battery storage project G1049, Harney County
Battery storage
650 MWWithdrawn / abandoned Harney, ORWest Nov 2023target 2029
Gas project J4111, Hot Spring County
Gas
650 MWWithdrawn / abandoned Hot Spring, ARMISO Oct 2025target 2030
Gas project G219, Johnson County
Gas
650 MWWithdrawn / abandoned Johnson, IAMISO Apr 2002target 2006
Gas project 247, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Apr 2008target 2012
Gas project 243, Gem County
Gas
650 MWWithdrawn / abandoned Gem, IDWest Apr 2008target 2012
South Bay Replacement - Option 1
Gas
650 MWWithdrawn / abandoned San Diego, CACAISO Feb 2004target 2010
Solar + storage project Q445, Maricopa County
Solar + storage
647 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2025
Gas project F05, Armstrong County
Gas
646 MWWithdrawn / abandoned Armstrong, PAPJM Jan 2001
CPV St. Charles
Gas
645 MWWithdrawn / abandoned Charles, MDPJM Oct 2006target 2013
Gas project G095, Wayne County
Gas
644 MWWithdrawn / abandoned Wayne, MIMISO Jun 2001target 2003
Ventus Renewable Energy Center
Other
643 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2023
Solar + storage project Q80, Apache County
Solar + storage
643 MWWithdrawn / abandoned Apache, AZWest Jun 2021target 2024
Gas project LGE-GIS-2007-004, Henderson County
Gas
642 MWWithdrawn / abandoned Henderson, KYSoutheast Apr 2007target 2011
Coal project J237, Henderson County
Coal
642 MWWithdrawn / abandoned Henderson, KYMISO Jul 2007target 2013
SR Bertron - CCGT
Gas · NRG Energy, Inc
641 MWWithdrawn / abandoned ERCOT Nov 2007target 2050
Solar project G0649, Wasco County
Solar
641 MWWithdrawn / abandoned Wasco, ORWest Jun 2020target 2023
Gas project IC-089, Covington County
Gas
640 MWWithdrawn / abandoned Covington, ALSoutheast
Solar + storage project Q77, Millard County
Solar + storage · Intermountain Power Agency
640 MWWithdrawn / abandoned Millard, UTWest Apr 2020target 2023
Other project 91, Dickson County
Other
640 MWWithdrawn / abandoned Dickson, TNSoutheast Mar 2000
Gas project GEN-2001-005, Curry County
Gas
640 MWWithdrawn / abandoned Curry, NMSPP Jan 2001
Other project 92, Union County
Other
640 MWWithdrawn / abandoned Union, MSSoutheast Mar 2000
Onshore wind project GI-2016-27, Elbert County
Onshore wind
640 MWWithdrawn / abandoned Elbert, COWest Nov 2016target 2019
Duke Energy NA
Gas · Duke Energy North America, LLC
640 MWWithdrawn / abandoned Deschutes, ORWest Dec 2001target 2005
Other project 90, Maury County
Other
640 MWWithdrawn / abandoned Maury, TNSoutheast Mar 2000
Other project 132, Metcalfe County
Other
640 MWWithdrawn / abandoned Metcalfe, KYSoutheast Nov 2000
Gas project GEN-2001-010, Leavenworth County
Gas
640 MWWithdrawn / abandoned Leavenworth, KSSPP Mar 2001
Gas project GEN-2001-002, Johnson County
Gas
640 MWWithdrawn / abandoned Johnson, KSSPP Jan 2001
Gas project IC-088, Dale County
Gas
640 MWWithdrawn / abandoned Dale, ALSoutheast
Gas project O04, Camden County
Gas
640 MWWithdrawn / abandoned Camden, NJPJM Feb 2005target 2008
Other project 85, Haywood County
Other
640 MWWithdrawn / abandoned Haywood, TNSoutheast Mar 2000
Gas project U2-048, Burlington County
Gas
640 MWWithdrawn / abandoned Burlington, NJPJM Jun 2008target 2012
Gas project IC-085, Escambia County
Gas
640 MWWithdrawn / abandoned Escambia, ALSoutheast
Gas project IC-087, Tift County
Gas
640 MWWithdrawn / abandoned Tift, GASoutheast
Gas project IC-1219, Hart County
Gas
640 MWWithdrawn / abandoned Hart, GASoutheast Dec 2023
Gas project GEN-2001-009, Leavenworth County
Gas
640 MWWithdrawn / abandoned Leavenworth, KSSPP Mar 2001target 2003
Blythe III (Revised)
Gas
640 MWWithdrawn / abandoned Riverside, CACAISO Jun 2007target 2015
Gas project IC-072, Mitchell County
Gas
640 MWWithdrawn / abandoned Mitchell, GASoutheast
Other project 133, Marshall County
Other
640 MWWithdrawn / abandoned Marshall, KYSoutheast Nov 2000
Other project 124, Mccracken County
Other
640 MWWithdrawn / abandoned Mccracken, KYSoutheast Nov 2000
Solar + storage project C4-026, Harney County
Solar + storage
640 MWWithdrawn / abandoned Harney, ORWest May 2024target 2028
Gas project 17, Polk County
Gas · Duke Energy Florida, LLC
640 MWWithdrawn / abandoned Polk, FLSoutheast Jul 2002
Gas project LGE-GIS-2007-003, Henderson County
Gas
640 MWWithdrawn / abandoned Henderson, KYSoutheast Mar 2007target 2011
Gas project IC-1218, Lee County
Gas
640 MWWithdrawn / abandoned Lee, ALSoutheast Dec 2023
Gas project E17_W29, Westmoreland County
Gas
640 MWWithdrawn / abandoned Westmoreland, PAPJM Nov 2000target 2005
Gas project IC-008, Autauga County
Gas
640 MWWithdrawn / abandoned Autauga, ALSoutheast
Page 26 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)