United States βΊ Grid βΊ Interconnection queues βΊ Oregon
GAS Β· WESTDuke Energy NA
Duke Energy NA is a 640 MW gas request withdrawn in the West interconnection queue, in Deschutes County, Oregon, connecting to Duke Energy North America, LLC.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2001 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G91
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Duke Energy North America, LLC
- Developer
- Duke Energy North America, LLC
- Connection point (POI)
- BPA's 230 kV transmission line between Redmond and Pilot Butte substations in Deschutes Co., OR
- Location
- Deschutes County, Oregon
- Technology
- Gas: 640 MW
- Total requested
- 640 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 20 December 2001
- Proposed online date
- June 2005
Location
Marker shows the centre of Deschutes County; the queue data does not give exact sites.
Other requests in Deschutes County
- Solar project G0539, Deschutes CountySolar Β· 600 MW Β· agreement signed
- Solar + storage project G1052, Deschutes CountySolar + storage Β· 2,600 MW Β· in study
- Solar + storage project G1051, Deschutes CountySolar + storage Β· 2,600 MW Β· in study
- Solar + storage project G1050, Deschutes CountySolar + storage Β· 1,300 MW Β· in study
- Battery storage project G1056, Deschutes CountyBattery storage Β· 650 MW Β· in study
- Onshore wind project G0861, Deschutes CountyOnshore wind Β· 500 MW Β· in study
- Solar + storage project G0910, Deschutes CountySolar + storage Β· 400 MW Β· in study
- Solar + storage project G0912, Deschutes CountySolar + storage Β· 400 MW Β· in study
- Solar + storage project G0909, Deschutes CountySolar + storage Β· 400 MW Β· in study
- Geothermal project G1078, Deschutes CountyGeothermal Β· 54.0 MW Β· in study
- Solar project G1071, Deschutes CountySolar Β· 1.0 MW Β· in study
- Solar project T2-089, Deschutes CountySolar Β· 0.4 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem