United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2020 requests) โ€” page 24

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests ยท page 24 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Hanson Energy Center
Battery storage
30.8 MWWithdrawn / abandoned Santa Barbara, CACAISO Apr 2020target 2023
Apricot Energy Storage
Battery storage
30.6 MWWithdrawn / abandoned Fresno, CACAISO Apr 2020target 2023
Crowswest
Solar + storage
30.2 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2020target 2023
Solar project AG2-031, Stark County
Solar
30.2 MWWithdrawn / abandoned Stark, OHPJM Oct 2020target 2023
Weirton Solar 24 kV
Solar
30.0 MWWithdrawn / abandoned Hancock, WVPJM Jun 2020target 2024
Battery storage project IA-PNM-2020-02, Bernalillo County
Battery storage
30.0 MWWithdrawn / abandoned Bernalillo, NMWest Jan 2020target 2022
Merry Point Solar
Solar ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
30.0 MWWithdrawn / abandoned Lancaster, VAPJM Sep 2020target 2024
Battery storage project 384, Yellowstone County
Battery storage
30.0 MWWithdrawn / abandoned Yellowstone, MTWest Jun 2020target 2023
Battery storage project AG1-371, Lee County
Battery storage ยท Steward Creek Solar, LLC
30.0 MWWithdrawn / abandoned Lee, ILPJM Sep 2020target 2024
Battery storage project 383, Missoula County
Battery storage
30.0 MWWithdrawn / abandoned Missoula, MTWest Jun 2020target 2023
Solar project AG1-283, Monroe County
Solar
30.0 MWWithdrawn / abandoned Monroe, PAPJM Sep 2020target 2023
Cuckoo Energy Storage
Battery storage
30.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2022
Solar project AG1-461, Sussex County
Solar
30.0 MWWithdrawn / abandoned Sussex, DEPJM Sep 2020target 2023
Solar project AG1-392, Potter County
Solar ยท PO-Cowburn LLC
30.0 MWWithdrawn / abandoned Potter, PAPJM Sep 2020target 2022
Battery storage project J1806, Henry County
Battery storage
30.0 MWWithdrawn / abandoned Henry, INMISO Jun 2020target 2022
Battery storage project AG1-376, Blackford County
Battery storage
30.0 MWWithdrawn / abandoned Blackford, INPJM Sep 2020target 2024
Solar project AG1-392A, Potter County
Solar ยท PO-Cowburn LLC
30.0 MWWithdrawn / abandoned Potter, PAPJM Oct 2020target 2022
Battery storage project 385, Lewis And Clark County
Battery storage
30.0 MWWithdrawn / abandoned Lewis And Clark, MTWest Jun 2020target 2023
Battery storage project AG1-456, Highland County
Battery storage ยท Willowbrook Solar I, LLC
30.0 MWWithdrawn / abandoned Highland, OHPJM Sep 2020target 2022
Offshore wind project AF2-196, Sussex County
Offshore wind
30.0 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2022
Battery storage project 382, Gallatin County
Battery storage
30.0 MWWithdrawn / abandoned Gallatin, MTWest Jun 2020target 2023
Solar + storage project IC-889, Dodge County
Solar + storage
30.0 MWWithdrawn / abandoned Dodge, GASoutheast Jul 2020target 2023
Solar project 126064, Cherokee County
Solar
30.0 MWWithdrawn / abandoned Cherokee, SCSoutheast Mar 2020
Battery storage project 386, Gallatin County
Battery storage
30.0 MWWithdrawn / abandoned Gallatin, MTWest Jun 2020target 2023
Battery storage project AG1-089
Battery storage
30.0 MWWithdrawn / abandoned WVPJM Jul 2020target 2021
Solar project IC-918, Mitchell County
Solar
30.0 MWWithdrawn / abandoned Mitchell, GASoutheast Nov 2020
Eversource Group @ Industrial Park 636
Solar + storage
29.1 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2023
Battery storage project AF2-308, Hardin County
Battery storage
28.0 MWWithdrawn / abandoned Hardin, KYPJM Mar 2020target 2023
Eversource Group @ Fisher Rd Substation 657
Solar + storage
27.9 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2023
Solar project AG1-162, Mason County
Solar
27.4 MWWithdrawn / abandoned Mason, WVPJM Sep 2020target 2022
Freeborn
Solar
27.3 MWWithdrawn / abandoned Kern, CACAISO Apr 2020target 2023
Solar
Solar
27.0 MWWithdrawn / abandoned Grafton, NHISO-NE Dec 2020target 2022
Solar project AG1-381, Montgomery County
Solar
27.0 MWWithdrawn / abandoned Montgomery, KYPJM Sep 2020target 2023
Blue Hill Wind
Onshore wind ยท Liberty Renewables Inc.
27.0 MWWithdrawn / abandoned Madison, NYNYISO Nov 2020
Otay Mesa Energy Center Expansion
Gas
26.4 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2022
Battery storage project 138678, Buncombe County
Battery storage ยท Duke Energy Progress, LLC
26.3 MWWithdrawn / abandoned Buncombe, NCSoutheast Oct 2020
Solar project J1511, Chisago County
Solar
26.0 MWWithdrawn / abandoned Chisago, MNMISO Jun 2020target 2023
Battery storage project AG1-445, Mecklenburg County
Battery storage ยท Fitzsimons Solar, LLC
26.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2020target 2023
Battery storage project AG1-446, Mecklenburg County
Battery storage ยท RWE Solar Development, LLC
26.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2020target 2023
Flat Top Solar
Battery storage
26.0 MWWithdrawn / abandoned Barren, KYPJM Mar 2020target 2027
Solar project AG1-131, Shenandoah County
Solar
25.6 MWWithdrawn / abandoned Shenandoah, VAPJM Sep 2020target 2022
Solar project AF2-301, Isle Of Wight County
Solar
25.0 MWWithdrawn / abandoned Isle Of Wight, VAPJM Mar 2020target 2023
Timberwolf BESS
Other ยท Crane BESS, LLC
25.0 MWWithdrawn / abandoned Upton, TXERCOT Dec 2020target 2022
Solar project 126048, Spartanburg County
Solar
25.0 MWWithdrawn / abandoned Spartanburg, SCSoutheast Mar 2020
Onshore wind project J1800, Mower County
Onshore wind
25.0 MWWithdrawn / abandoned Mower, MNMISO Jun 2020target 2023
Solar project AF2-259, Chesterfield County
Solar
25.0 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2020target 2022
Choptank Solar and Storage
Battery storage ยท RWE Solar Development, LLC
25.0 MWWithdrawn / abandoned Dorchester, MDPJM Sep 2020target 2022
Eversource Group @ Rochester #745
Solar + storage
24.6 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Solar project AF2-357, Washington County
Solar
24.0 MWWithdrawn / abandoned Washington, MDPJM Mar 2020target 2023
Richardson Solar
Solar ยท AES DE DEVCO NC LLC
24.0 MWWithdrawn / abandoned St. Lawrence, NYNYISO Aug 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)