United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2018 requests) โ page 24
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AE1-201, Mchenry County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE1-005, Beaufort County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-186, Berks County Solar |
20.0 MW | Withdrawn / abandoned |
| Slate Hill 1 Solar Solar ยท EDF Renewable Development Inc. |
20.0 MW | Withdrawn / abandoned |
| Titusville Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Hornell Storage Battery storage ยท Invenergy Solar Development North America LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-199, Ogle County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Edora B Solar Energy Center Solar ยท EDF Renewables Development, Inc. |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-009, Fluvanna County Solar |
20.0 MW | Withdrawn / abandoned |
| Champlain Solar Solar ยท EDF Renewables Development, Inc. |
20.0 MW | Withdrawn / abandoned |
| Brookview Solar I Solar |
20.0 MW | Withdrawn / abandoned |
| VSF Solar I Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-008, Preble County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 57, Adams County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AD2-056, Henrico County Solar |
20.0 MW | Withdrawn / abandoned |
| Manchester Solar Solar ยท SED NY Holdings LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AD2-125, Somerset County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Whitetail VI Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AE1-231, Charles County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Fayetteville Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE1-115, Salem County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Suffragette Solar Energy Center Solar ยท EDF Renewables Development, Inc. |
20.0 MW | Withdrawn / abandoned |
| Solar project 102, Darlington County Solar |
20.0 MW | Withdrawn / abandoned |
| Pinto Pass Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Rising Solar II Solar ยท Rising Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE1-088, Beaufort County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AE1-230, Pittsylvania County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AE1-145, Accomack County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AD2-124, Person County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AD2-095, Dorchester County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project J1041, Jackson County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Nittany Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Goshen Solar Solar ยท EDF Renewable Development Inc. |
20.0 MW | Withdrawn / abandoned |
| Johnstown Solar Solar ยท Hecate Energy Johnstown LLC |
20.0 MW | Withdrawn / abandoned |
| East Walden Solar Solar ยท EDF Renewable Development Inc. |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-165, Cambria County Solar |
20.0 MW | Withdrawn / abandoned |
| Kce NY 11 Battery storage ยท KCE NY 11 LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE1-062, Camden County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project 100, Aiken County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-180, Culpeper County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-076, Ogle County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AD2-094, Beaufort County Battery storage |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)306 ยท 50.5 GW
- PJM (Mid-Atlantic, Midwest)311 ยท 46.6 GW
- MISO (Midcontinent)165 ยท 28.2 GW
- Southeast (non-ISO utilities)248 ยท 28.2 GW
- CAISO (California)67 ยท 21.7 GW
- SPP (Southwest Power Pool)92 ยท 16.8 GW
- ERCOT (Texas)77 ยท 15.0 GW
- NYISO (New York)74 ยท 11.2 GW
- ISO-NE (New England)84 ยท 8,151 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)