πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

SOLAR Β· NYISO

Goshen Solar

Goshen Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Orange County, New York, connecting to O&R.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2018 (completed)
  2. Withdrawn / abandonedMar 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
689
Grid region
NYISO (New York)
Utility / transmission owner
O&R
Developer
EDF Renewable Development Inc.
Connection point (POI)
Huntley Station 115kV
Location
Orange County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
2 February 2018
Withdrawn
March 2018

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Orange County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem