Whitetail VI is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in St. Mary's County, Maryland, connecting to SMECO.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2018 (completed)
- Withdrawn / abandonedMar 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AE2-017
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- SMECO
- Connection point (POI)
- Lexington Park 69 kV
- Location
- St. Mary's County, Maryland
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 28 November 2018
- Proposed online date
- March 2023
- Withdrawn
- March 2021
Location
Marker shows the centre of St. Mary's County; the queue data does not give exact sites.
Other requests in St. Mary's County
- Gas project G35, St. Mary's CountyGas Β· 340 MW Β· withdrawn
- Solar project AH1-643, St. Mary's CountySolar Β· 80.0 MW Β· withdrawn
- Solar project AD2-174, St. Mary's CountySolar Β· 52.5 MW Β· withdrawn
- Solar project X1-025, St. Mary's CountySolar Β· 10.0 MW Β· withdrawn
- Solar project X1-022, St. Mary's CountySolar Β· 10.0 MW Β· withdrawn
- Solar project X1-023, St. Mary's CountySolar Β· 6.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem