Solar project AD2-174, St. Mary's County

Solar project AD2-174, St. Mary's County is a 52.5 MW solar request withdrawn in the PJM interconnection queue, in St. Mary's County, Maryland, connecting to SMECO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD2-174
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
SMECO
Connection point (POI)
Oakville-St. Andrews 69kV
Location
St. Mary's County, Maryland
Technology
Solar: 52.5 MW
Total requested
52.5 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
28 March 2018
Proposed online date
September 2020
Withdrawn
January 2019

Location

Marker shows the centre of St. Mary's County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in St. Mary's County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem