Solar project 102, Darlington County

Solar project 102, Darlington County is a 20.0 MW solar request withdrawn in the Southeast interconnection queue, in Darlington County, South Carolina, connecting to Santee Cooper.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
102
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Santee Cooper
Location
Darlington County, South Carolina
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
11 May 2018
Proposed online date
July 2019

Location

Marker shows the centre of Darlington County; the queue data does not give exact sites.

Power plants in South Carolina Β· Transmission lines in South Carolina

Other requests in Darlington County