🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 235

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 235 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Baker Solar I
Solar
100 MWWithdrawn / abandoned Riverside, CACAISO Jun 2008target 2010
Gas Turbine
Gas
100 MWWithdrawn / abandoned Norfolk, MAISO-NE Apr 2007target 2011
Solar + storage project IA-PNM-2023-13, Valencia County
Solar + storage
100 MWWithdrawn / abandoned Valencia, NMWest Jan 2023target 2026
Solar project AG2-510, Clarke County
Solar
100 MWWithdrawn / abandoned Clarke, VAPJM Mar 2021target 2024
Onshore wind project Q29, Cochise County
Onshore wind
100 MWWithdrawn / abandoned Cochise, AZWest Jul 2007target 2010
Onshore wind project J1116, Hancock County
Onshore wind
100 MWWithdrawn / abandoned Hancock, INMISO Mar 2018target 2021
Onshore wind project 18-05102, Larimer County
Onshore wind
100 MWWithdrawn / abandoned Larimer, COWest May 2018target 2020
Battery storage project AI1-107, Chesterfield County
Battery storage
100 MWWithdrawn / abandoned Chesterfield, VAPJM Aug 2022target 2028
Onshore wind project J730, Clark County
Onshore wind
100 MWWithdrawn / abandoned Clark, SDMISO Nov 2016target 2019
Solar project IC-923, Pearl River County
Solar
100 MWWithdrawn / abandoned Pearl River, MSSoutheast Dec 2020
Solar + storage project GEN-2021-080, Lea County
Solar + storage
100 MWWithdrawn / abandoned Lea, NMSPP Apr 20212024
Battery storage project GEN-2021-002, Blaine County
Battery storage
100 MWWithdrawn / abandoned Blaine, OKSPP Dec 2020target 2027
Solar project AD2-147, Butler County
Solar
100 MWWithdrawn / abandoned Butler, OHPJM Mar 2018target 2020
Coal project GI-0205, Adams County
Coal
100 MWWithdrawn / abandoned Adams, NDWest Apr 2002
Solar project J3150, Panola County
Solar
100 MWWithdrawn / abandoned Panola, MSMISO Sep 2022target 2027
Solar + storage project J2905, Washington County
Solar + storage
100 MWWithdrawn / abandoned Washington, MSMISO Sep 2022target 2025
Battery storage project AG2-506, Dinwiddie County
Battery storage
100 MWWithdrawn / abandoned Dinwiddie, VAPJM Mar 2021target 2024
Battery storage project AH2-272, Mecklenburg County
Battery storage
100 MWWithdrawn / abandoned Mecklenburg, VAPJM Mar 2022target 2027
Alta Q153 (Fka Alta 7)
Onshore wind
100 MWWithdrawn / abandoned Kern, CACAISO Nov 2006target 2016
Westtown Energy Storage
Battery storage · ACE DevCo NC, LLC
100 MWWithdrawn / abandoned Orange, NYNYISO Dec 2022
Tecate Hybrid
Solar + storage
100 MWWithdrawn / abandoned San Diego, CACAISO Jun 2006target 2022
Battery storage project C3-138, Kane County
Battery storage
100 MWWithdrawn / abandoned Kane, UTWest May 2023target 2027
Battery storage project J2460, Jefferson County
Battery storage
100 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Onshore wind project GEN-2009-053, Ford County
Onshore wind
100 MWWithdrawn / abandoned Ford, KSSPP Dec 2009target 2011
PSEG Fossil Bergen Unit 2
Gas · In City I, LLC
100 MWWithdrawn / abandoned NYNYISO Jan 2008
Onshore wind project GEN-2014-050, Douglas County
Onshore wind
100 MWWithdrawn / abandoned Douglas, KSSPP Sep 2014target 2016
Solar project J2470, Rapides Parish County
Solar
100 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2022target 2026
Orion Energy NY I
Onshore wind · BP Alternative Energy NA, Inc.
100 MWWithdrawn / abandoned Herkimer, NYNYISO Oct 2004
Solar project 20171018010, Orangeburg County
Solar
100 MWWithdrawn / abandoned Orangeburg, SCSoutheast target 2019
Solar project J621, Lincoln County
Solar
100 MWWithdrawn / abandoned Lincoln, ARMISO May 2016target 2018
Onshore wind project 24, Carbon County
Onshore wind
100 MWWithdrawn / abandoned Carbon, MTWest Feb 2003
Solar project J1634, Beauregard Parish County
Solar
100 MWWithdrawn / abandoned Beauregard Parish, LAMISO Jun 2020target 2022
Solar project Company HR, Lyon County
Solar
100 MWWithdrawn / abandoned Lyon, NVWest Sep 2017target 2021
Solar project AH1-551, Carroll County
Solar
100 MWWithdrawn / abandoned Carroll, OHPJM Sep 2021target 2025
Battery storage project AG2-323, Loudoun County
Battery storage
100 MWWithdrawn / abandoned Loudoun, VAPJM Mar 2021target 2023
Solar + storage project C2-125, Marion County
Solar + storage
100 MWWithdrawn / abandoned Marion, ORWest May 2022target 2025
Onshore wind project G662, Corson County
Onshore wind
100 MWWithdrawn / abandoned Corson, SDMISO Jul 2006target 2007
Battery storage project Q59, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Jun 2019target 2023
Solar project Q179, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2014
Solar + storage project Company PG, White Pine County
Solar + storage
100 MWWithdrawn / abandoned White Pine, NVWest Mar 2023target 2025
Coral Storage Project
Battery storage · Hanwha Q CELLS USA
100 MWWithdrawn / abandoned Chemung, NYNYISO Nov 2021
Cayuga Solar
Solar · ACE DevCo NC, LLC
100 MWWithdrawn / abandoned Tompkins, NYNYISO Feb 2023
Lucerne Solar Energy - C5
Solar
100 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2012target 2015
Texas Plains Windpark
Onshore wind · Noble Environmental Power
100 MWWithdrawn / abandoned ERCOT Feb 2008
Onshore wind project S45, Champaign County
Onshore wind
100 MWWithdrawn / abandoned Champaign, OHPJM May 2007target 2009
Onshore wind project GEN-2008-099, Coffey County
Onshore wind
100 MWWithdrawn / abandoned Coffey, KSSPP Aug 2008target 2011
Onshore wind project J082, Mercer County
Onshore wind
100 MWWithdrawn / abandoned Mercer, NDMISO Oct 2009target 2013
Solar project AE2-328, Accomack County
Solar
100 MWWithdrawn / abandoned Accomack, VAPJM Mar 2019target 2022
Onshore wind project C2-42, Umatilla County
Onshore wind
100 MWWithdrawn / abandoned Umatilla, ORWest Apr 2022target 2025
Solar project J1278, Polk County
Solar
100 MWWithdrawn / abandoned Polk, TXMISO Apr 2019target 2022
Page 235 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)