United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOCayuga Solar
Cayuga Solar is a 100 MW solar request withdrawn in the NYISO interconnection queue, in Tompkins County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1509
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- ACE DevCo NC, LLC
- Connection point (POI)
- Milliken (Cayuga) 115 kV Substation
- Location
- Tompkins County, New York
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Queue status
- Withdrawn
- Entered queue
- 1 February 2023
Location
Marker shows the centre of Tompkins County; the queue data does not give exact sites.
Other requests in Tompkins County
- BPP NY Lansing BESS IBattery storage Β· 200 MW Β· in study
- Yellow Barn SolarSolar Β· 160 MW Β· in study
- Cayuga SolarSolar Β· 60.0 MW Β· in study
- Troy Heights Energy StorageBattery storage Β· 40.0 MW Β· in study
- Cayuga SolarSolar Β· 207 MW Β· withdrawn
- BPP NY Lansing BESS IBattery storage Β· 200 MW Β· withdrawn
- Yellow Barn SolarSolar Β· 160 MW Β· withdrawn
- Silverline Energy CenterSolar + storage Β· 150 MW Β· withdrawn
- Argos SolarSolar Β· 150 MW Β· withdrawn
- Silverline Energy CenterSolar + storage Β· 150 MW Β· withdrawn
- Queen Energy CenterBattery storage Β· 140 MW Β· withdrawn
- Black Oak WindOnshore wind Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem