🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

SOLAR + STORAGE · NYISO

Silverline Energy Center

Silverline Energy Center is a 150 MW solar + storage request withdrawn in the NYISO interconnection queue, in Tompkins County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1041
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Silverline Energy Center, LLC
Connection point (POI)
Miliken - Etna 115 kV lines 974 and 975
Location
Tompkins County, New York
Technology
Solar: 150 MW · Battery
Total requested
150 MW
Queue status
Withdrawn
Entered queue
25 June 2020

Location

Marker shows the centre of Tompkins County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Tompkins County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem