Yellow Barn Solar is a 160 MW solar request in interconnection study in the NYISO interconnection queue, in Tompkins County, New York, connecting to NYSEG.

Queue statusIn planning
  1. PlanningQueued Apr 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1009
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Yellow Barn Solar, LLC
Connection point (POI)
Milliken - Etna 115 kV line #975
Location
Tompkins County, New York
Technology
Solar: 160 MW
Total requested
160 MW
Study phase
SRIS, FS
Queue status
Active
Entered queue
30 April 2020
Proposed online date
December 2028

Location

Marker shows the centre of Tompkins County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Tompkins County