Tecate Hybrid

Tecate Hybrid is a 100 MW solar + storage request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2006 (completed)
  2. Withdrawn / abandonedDec 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
106A
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Boulevard East Substation 138kV
Location
San Diego County, California
Technology
Solar: 50.0 MW · Battery: 50.0 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Withdrawn
Entered queue
6 June 2006
Proposed online date
December 2022
Withdrawn
December 2019

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Diego County