United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2022 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,886378.9 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,886 requests ยท page 2 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G0816, Grays Harbor County
Onshore wind
1,000 MWWithdrawn / abandoned Grays Harbor, WAWest Oct 2022target 2030
Solar + storage project LGE-GIS-2022-006, Clarke County
Solar + storage
1,000 MWWithdrawn / abandoned Clarke, INSoutheast Aug 2022target 2029
Solar + storage project Q32, Maricopa County
Solar + storage
1,000 MWWithdrawn / abandoned Maricopa, AZWest Sep 2022target 2025
Wind
Onshore wind
905 MWWithdrawn / abandoned Aroostook, MEISO-NE May 2022target 2026
NY Interconnection 4
Offshore wind ยท NY Interconnection LLC
900 MWWithdrawn / abandoned New York, NYNYISO Jun 2022
Solar project GEN-2022-052, Bossier Parish County
Solar
850 MWWithdrawn / abandoned Bossier Parish, LASPP Jun 20222025
Solar + storage project J2911, Beauregard Parish County
Solar + storage
810 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2027
Solar + storage project Q27, Pinal County
Solar + storage
800 MWWithdrawn / abandoned Pinal, AZWest Nov 2022target 2026
Solar + storage project Q92, Maricopa County
Solar + storage
800 MWWithdrawn / abandoned Maricopa, AZWest Apr 2022target 2024
Gas project 569364, Cherokee County
Gas
757 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2022
Gas project 564266, Cherokee County
Gas
757 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2022
Tehuacana Creek Solar-Alt POI
Solar ยท Tehuacana Creek Solar LLC
715 MWWithdrawn / abandoned Freestone, TXERCOT Oct 2022target 2025
Solar project GEN-2022-086, Finney County
Solar
700 MWWithdrawn / abandoned Finney, KSSPP Nov 2022target 2027
Gas project J3089, Webster County
Gas
696 MWWithdrawn / abandoned Webster, KYMISO Sep 2022target 2029
Gas project LGE-GIS-2022-011, Mercer County
Gas
660 MWWithdrawn / abandoned Mercer, KYSoutheast Oct 2022target 2028
Gas project LGE-GIS-2022-004, Mercer County
Gas
660 MWWithdrawn / abandoned Mercer, KYSoutheast Jun 2022target 2027
Goldenrod Creek Solar
Solar ยท Goldenrod Creek Solar LLC
660 MWWithdrawn / abandoned Jackson, TXERCOT Feb 2022target 2025
Battery storage project G0798, Wasco County
Battery storage
650 MWWithdrawn / abandoned Wasco, ORWest Aug 2022target 2029
Solar project J2595, Hinds County
Solar
650 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2026
Battery storage project G0786, Morrow County
Battery storage
650 MWWithdrawn / abandoned Morrow, ORWest Aug 2022target 2029
Battery storage project G0782, Morrow County
Battery storage
650 MWWithdrawn / abandoned Morrow, ORWest Aug 2022target 2029
Solar project J2594, Hinds County
Solar
650 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2026
Solar project G0785, Morrow County
Solar
650 MWWithdrawn / abandoned Morrow, ORWest Aug 2022target 2028
Solar + storage project Q445, Maricopa County
Solar + storage
647 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2025
Solar + storage project Q490, Mohave County
Solar + storage
600 MWWithdrawn / abandoned Mohave, AZWest Sep 2022target 2026
Solar + storage project G0755, Klamath County
Solar + storage
600 MWWithdrawn / abandoned Klamath, ORWest Jun 2022target 2025
Battery storage project G0784, Wasco County
Battery storage
600 MWWithdrawn / abandoned Wasco, ORWest Aug 2022target 2029
Solar + storage project G0813, Umatilla County
Solar + storage
600 MWWithdrawn / abandoned Umatilla, ORWest Sep 2022target 2026
Solar + storage project Q95, Navajo County
Solar + storage
600 MWWithdrawn / abandoned Navajo, AZWest Jul 2022target 2025
Onshore wind project C2-46, Laramie County
Onshore wind
600 MWWithdrawn / abandoned Laramie, WYWest Apr 2022target 2025
Battery storage project G0776, Wasco County
Battery storage
600 MWWithdrawn / abandoned Wasco, ORWest Aug 2022target 2028
Solar + storage project G0750, Sanders County
Solar + storage
600 MWWithdrawn / abandoned Sanders, MTWest Jun 2022target 2025
Solar + storage project G0736, Asotin County
Solar + storage
600 MWWithdrawn / abandoned Asotin, WAWest Mar 2022target 2025
Battery storage project G0780, Wasco County
Battery storage
600 MWWithdrawn / abandoned Wasco, ORWest Aug 2022target 2029
Sandlot
Battery storage ยท Sandlot Energy LLC
600 MWWithdrawn / abandoned Suffolk, NYNYISO Dec 2022
Battery storage project G0788, Wasco County
Battery storage
600 MWWithdrawn / abandoned Wasco, ORWest Aug 2022target 2028
Onshore wind project C2-43, Sweetwater County
Onshore wind
600 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2022target 2025
Solar project G0783, Wasco County
Solar
600 MWWithdrawn / abandoned Wasco, ORWest Aug 2022target 2028
Solar + storage project Q87, Beaver County
Solar + storage ยท Intermountain Power Agency
600 MWWithdrawn / abandoned Beaver, UTWest Feb 2022target 2024
New Scotland BESS Project
Battery storage ยท Capital Region Energy Storage LLC
600 MWWithdrawn / abandoned Albany, NYNYISO Oct 2022
Leeds BESS Project
Battery storage ยท Capital Region Energy Storage LLC
600 MWWithdrawn / abandoned Greene, NYNYISO Nov 2022
Solar + storage project G0749, Powell County
Solar + storage
600 MWWithdrawn / abandoned Powell, MTWest Jun 2022target 2025
Battery storage project G0809, Douglas County
Battery storage
600 MWWithdrawn / abandoned Douglas, ORWest Sep 2022target 2030
Solar + storage project J2717, Hot Spring County
Solar + storage
600 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2029
Battery storage project IA-PNM-2022-01, San Juan County
Battery storage
600 MWWithdrawn / abandoned San Juan, NMWest Jan 2022target 2028
Onshore wind project AH2-287, Monmouth County
Onshore wind
600 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2022target 2029
Onshore wind project C2-104, Lincoln County
Onshore wind
600 MWWithdrawn / abandoned Lincoln, WYWest May 2022target 2025
Battery storage project G0725, Coos County
Battery storage
600 MWWithdrawn / abandoned Coos, ORWest Jan 2022target 2027
Gas project J3215, Laporte County
Gas
594 MWWithdrawn / abandoned Laporte, INMISO Sep 2022target 2025
Solar + storage project 22-113, Lake County
Solar + storage
560 MWWithdrawn / abandoned Lake, ORWest Nov 2022target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)