Completed queue projects in the USA (2016 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31336.6 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

313 requests ยท page 2 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2016-151, Burke County
Onshore wind
202 MWOperating Burke, NDSPP Nov 20162020
Onshore wind project J728, Isabella County
Onshore wind
200 MWOperating Isabella, MIMISO Nov 20162020
Onshore wind project J717, Isabella County
Onshore wind
200 MWOperating Isabella, MIMISO Sep 20162020
Onshore wind project GEN-2016-032, Kingfisher County
Onshore wind
200 MWOperating Kingfisher, OKSPP Mar 20162024
Onshore wind project J587, Lincoln County
Onshore wind
200 MWOperating Lincoln, MNMISO May 20162020
Onshore wind project J748, Plymouth County
Onshore wind
200 MWOperating Plymouth, IAMISO Nov 20162021
Onshore wind project J583, Audubon County
Onshore wind
200 MWOperating Audubon, IAMISO May 20162021
Solar project J758, Calhoun County
Solar
200 MWOperating Calhoun, MIMISO Nov 20162022
Solar + storage project 778, Emery County
Solar + storage ยท Hornshadow Solar 2, LLC
200 MWOperating Emery, UTWest Jul 2016target 2024
Onshore wind project GEN-2016-094, Hyde County
Onshore wind
200 MWOperating Hyde, SDSPP Oct 20162024
Solar project 763, Iron County
Solar ยท Appaloosa Solar I, LLC
200 MWOperating Iron, UTWest Jun 2016target 2023
Top Hat Wind Energy Center
Onshore wind
200 MWOperating Logan, ILPJM Sep 20162025
Alta Farms II
Onshore wind
197 MWOperating Dewitt, ILPJM Mar 20162023
Onshore wind project 835, Carbon County
Onshore wind ยท PacifiCorp
190 MWOperating Carbon, WYWest Dec 2016target 2024
Solar + storage project Q23, Maricopa County
Solar + storage
183 MWOperating Maricopa, AZWest Jun 20162023
Solar + storage project ANPP HVS-Q23
Solar + storage
183 MWOperating West Jun 2016target 2023
Sagebrush Solar 2
Battery storage
179 MWOperating Kern, CACAISO May 20162024
Big Plain
Solar
176 MWOperating Madison, OHPJM Oct 20162023
Onshore wind project GEN-2016-126, Murray County
Onshore wind
173 MWOperating Murray, OKSPP Nov 20162021
Wadley Solar
Solar
170 MWOperating Jefferson, GASoutheast Jul 20162024
Gas project 205
Gas
160 MWOperating Southeast Sep 20162019
Barrow Ranch Wind
Onshore wind ยท Engie
160 MWOperating Andrews, TXERCOT Oct 20162021
Fowler Ranch
Solar ยท CED Crane Solar, LLC
153 MWOperating Crane, TXERCOT Oct 20162020
Tropico Solar
Solar + storage
152 MWOperating Kern, CACAISO May 20162022
Onshore wind project GEN-2016-022, Kay County
Onshore wind
152 MWOperating Kay, OKSPP Mar 20162020
Mustang Creek Solar
Solar ยท Ganado Solar, LLC
151 MWOperating Jackson, TXERCOT Nov 20162023
Onshore wind project CLPT G8, Laramie County
Onshore wind ยท Roundhouse Interconnect, LLC
150 MWOperating Laramie, WYWest Dec 2016target 2023
Willowbrook Solar
Solar
150 MWOperating Highland, OHPJM Oct 20162024
Fort Powhatan Solar
Solar
150 MWOperating Prince George, VAPJM Apr 20162022
Onshore wind project GEN-2016-124, Roosevelt County
Onshore wind
150 MWOperating Roosevelt, NMSPP Nov 20162020
Solar project 297, Lincoln County
Solar
150 MWOperating Lincoln, TNSoutheast Jun 2016
Solar project Q21, Maricopa County
Solar
150 MWOperating Maricopa, AZWest Jan 20162021
Solar project ANPP HVS-Q21
Solar
150 MWOperating West Jan 2016target 2021
Onshore wind project J589, Gratiot County
Onshore wind
149 MWOperating Gratiot, MIMISO May 20162018
Onshore wind project GEN-2016-020, Woodward County
Onshore wind
148 MWOperating Woodward, OKSPP Apr 20162020
Palmas Altas Wind
Onshore wind ยท Acciona
145 MWOperating Cameron, TXERCOT Mar 20162020
Onshore wind project 49, Adams County
Onshore wind
144 MWOperating Adams, WAWest Nov 2016target 2020
Tavener Solar
Solar ยท Fort Bend Solar LLC
144 MWOperating Fort Bend, TXERCOT Dec 20162023
Colonial Trail West Solar
Solar
142 MWOperating Surry, VAPJM Apr 20162019
Onshore wind project J555, Poweshiek County
Onshore wind
140 MWOperating Poweshiek, IAMISO Mar 20162017
Onshore wind project 46, Lewis County
Onshore wind
137 MWOperating Lewis, WAWest Jan 20162019
Onshore wind project GEN-2016-153, Harper County
Onshore wind
134 MWOperating Harper, KSSPP Nov 20162025
Hardin Energy Center
Solar
130 MWOperating Hardin, OHPJM Apr 20162020
Gas project J703, Marquette County
Gas
128 MWOperating Marquette, MIMISO Sep 20162018
Solar project Q22, Maricopa County
Solar
125 MWOperating Maricopa, AZWest Feb 2016target 2025
Solar project 737, Washington County
Solar ยท Cove Mountain Solar 2, LLC
122 MWOperating Washington, UTWest Apr 2016target 2020
Shillelagh Solar
Solar
118 MWOperating City Of Chesapeake, VAPJM Dec 20162023
Daggett Solar 1
Battery storage
114 MWOperating San Bernardino, CACAISO May 20162025
Bluestone Wind
Onshore wind ยท Bluestone Wind, LLC
112 MWOperating NYNYISO Sep 2016
Bluestone Wind
Onshore wind ยท Bluestone Wind, LLC
112 MWOperating Broome, NYNYISO Sep 20162023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)