United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTPalmas Altas Wind
Palmas Altas Wind is a 145 MW onshore wind request built and operating in the ERCOT interconnection queue, in Cameron County, Texas.
Request details
- Queue ID
- 17INR0037
- Grid region
- ERCOT (Texas)
- Developer
- Acciona
- Connection point (POI)
- 5760 PALMAS 138 kV
- Location
- Cameron County, Texas
- Technology
- Wind: 145 MW
- Total requested
- 145 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 23 March 2016
- Agreement signed
- 30 November 2017
- Proposed online date
- November 2020
- Came online
- November 2020
Location
Marker shows the centre of Cameron County; the queue data does not give exact sites.
Other requests in Cameron County
- Eval StorageBattery storage · 252 MW · agreement signed
- Pajarita BESSBattery storage · 206 MW · agreement signed
- Resaca Oasis StorageBattery storage · 201 MW · agreement signed
- Arroyo StorageSolar + storage · 184 MW · agreement signed
- Citrus Flatts BESSBattery storage · 101 MW · agreement signed
- Arroyo SolarSolar + storage · 100 MW · agreement signed
- Harlingen #1 BESS 1Battery storage · 10.0 MW · agreement signed
- Mesquite BESS2Battery storage · 10.0 MW · agreement signed
- Olmito BESSBattery storage · 10.0 MW · agreement signed
- East Harrison BESSBattery storage · 10.0 MW · agreement signed
- Laureles BESSBattery storage · 9.9 MW · agreement signed
- Mesquite BESSBattery storage · 9.9 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem