United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESProjects with signed interconnection agreements in the USA (2021 requests) โ page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project GEN-2021-005, Saline County Battery storage |
350 MW | Agreement signed |
| Briggs Storage Solar + storage ยท IP Quantum III, LLC |
336 MW | Agreement signed |
| Ariella Solar Solar + storage |
327 MW | Agreement signed |
| Spikes Peak Solar Solar + storage |
318 MW | Agreement signed |
| Haven Storage Battery storage |
313 MW | Agreement signed |
| Platinum Storage Battery storage ยท Platinum Energy Storage LLC |
310 MW | Agreement signed |
| Larkspur Energy Storage Battery storage ยท Larkspur Energy Storage LLC |
308 MW | Agreement signed |
| Solar project GEN-2021-023, Grant County Solar |
306 MW | Agreement signed |
| Lite Brite Battery Storage Battery storage |
306 MW | Agreement signed |
| Cuchillas Solar Solar + storage ยท Gransolar Texas Two, LLC |
306 MW | Agreement signed |
| Elion Energy Storage Battery storage |
302 MW | Agreement signed |
| Tyrell Energy Storage Battery storage |
302 MW | Agreement signed |
| Tabla Energy Storage Battery storage |
302 MW | Agreement signed |
| Jaguar Solar Solar + storage ยท PP Jaguar Solar LLC |
301 MW | Agreement signed |
| Solar + storage project Company MB, White Pine County Solar + storage |
300 MW | Agreement signed |
| Solar project GEN-2021-053, Muskogee County Solar |
300 MW | Agreement signed |
| Solar + storage project Company MA, White Pine County Solar + storage |
300 MW | Agreement signed |
| Solar + storage project IA-PNM-2021-10, Bernalillo County Solar + storage ยท NextEra Energy |
300 MW | Agreement signed |
| Onshore wind project GEN-2021-056, Harper County Onshore wind |
300 MW | Agreement signed |
| Solar + storage project C1-39, Washington County Solar + storage ยท REBU BN, LLC |
300 MW | Agreement signed |
| Solar + storage project Company MH, Churchill County Solar + storage |
300 MW | Agreement signed |
| Battery storage project Q375, Maricopa County Battery storage |
300 MW | Agreement signed |
| Electron Battery storage |
300 MW | Agreement signed |
| Aquilla Lake 3 Wind Onshore wind ยท Aquilla Lake 3 Wind |
297 MW | Agreement signed |
| Onshore wind project BHBE G16, Campbell County Onshore wind |
290 MW | Agreement signed |
| Solar + storage project Company 195, Clark County Solar + storage |
275 MW | Agreement signed |
| Blevins Solar Solar ยท Blevins Solar, LLC |
272 MW | Agreement signed |
| Pathfinder Storage Battery storage |
268 MW | Agreement signed |
| OCI SunRoper Solar ยท OCI SunRoper LLC |
265 MW | Agreement signed |
| Yellow Cat Wind Onshore wind ยท Yellow Cat Wind LLC |
262 MW | Agreement signed |
| Miranda Solar Project Solar ยท Miranda Solar Project, LLC |
261 MW | Agreement signed |
| Sypert Branch Solar Project Solar ยท Sypert Branch Solar LLC |
261 MW | Agreement signed |
| J90 Energy Storage Battery storage |
261 MW | Agreement signed |
| Commerce Energy Storage 3 Battery storage |
256 MW | Agreement signed |
| Zeya BESS Battery storage ยท BRP Zeya BESS LLC |
255 MW | Agreement signed |
| Ciervo Mountain Hybrid Solar + storage |
255 MW | Agreement signed |
| Sandrift Storage 1 Battery storage |
255 MW | Agreement signed |
| Sandrift Storage 2 Battery storage |
255 MW | Agreement signed |
| Roseland Solar II Solar ยท Enel Green Power Roseland Solar, LLC |
254 MW | Agreement signed |
| Greenwood Energy Storage Battery storage |
252 MW | Agreement signed |
| Zorin Storage Battery storage |
252 MW | Agreement signed |
| Tiger Solar Solar ยท Vaca Del Sol, LLC |
251 MW | Agreement signed |
| Battery storage project GEN-2021-043, Lancaster County Battery storage |
250 MW | Agreement signed |
| Solar project IC-950, Mcduffie County Solar |
250 MW | Agreement signed |
| Baylands Battery Battery storage |
250 MW | Agreement signed |
| Solar project GEN-2021-047, Mayes County Solar |
250 MW | Agreement signed |
| Hecate Energy Eastern Ave Energy Center Battery storage |
250 MW | Agreement signed |
| Solar + storage project 21-098, Jefferson County Solar + storage |
250 MW | Agreement signed |
| Lupinus Solar 2 Solar + storage ยท Lupinus Solar 2, LLC |
242 MW | Agreement signed |
| Solar project GEN-2021-018, Noble County Solar |
231 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)68 ยท 35.4 GW
- ERCOT (Texas)91 ยท 16.3 GW
- West (non-ISO utilities)55 ยท 11.7 GW
- ISO-NE (New England)17 ยท 3,473 MW
- SPP (Southwest Power Pool)19 ยท 3,459 MW
- Southeast (non-ISO utilities)12 ยท 1,908 MW
- MISO (Midcontinent)8 ยท 1,055 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)