United States › Grid › Interconnection queues › Mississippi

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Mississippi — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6914.2 GW
Active in queue17.0 GW93 requests
Agreement signed1,847 MW16 requests
Withdrawn31485.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

69 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-1244, Newton County
Solar
100 MWPaused / redesign Newton, MSSoutheast Mar 2024target 2029
Solar + storage project J3028, Perry County
Solar + storage
100 MWIn study Perry, MSMISO Sep 2022target 2027
Solar + storage project 25-IC-1337, Wayne County
Solar + storage
100 MWIn study Wayne, MSSoutheast Apr 2025target 2028
Solar + storage project J2763, Sunflower County
Solar + storage
100 MWIn study Sunflower, MSMISO Sep 2022target 2025
Battery storage project J3093, Madison County
Battery storage
100 MWIn study Madison, MSMISO Sep 2022target 2024
Battery storage project J4131, Scott County
Battery storage
100 MWIn study Scott, MSMISO Oct 2025target 2030
Solar project J2297, Sunflower County
Solar
100 MWIn study Sunflower, MSMISO Sep 2021target 2026
Solar + storage project J2957, Panola County
Solar + storage
100 MWIn study Panola, MSMISO Sep 2022target 2027
Solar project J4046, Attala County
Solar
100 MWIn study Attala, MSMISO Jul 2025target 2030
Solar + storage project J3186, Bolivar County
Solar + storage
100 MWIn study Bolivar, MSMISO Sep 2022target 2027
Surplus; J908
Battery storage
100 MWIn study Tallahatchie, MSMISO Aug 2025target 2027
Solar project J2761, Marion County
Solar
100 MWIn study Marion, MSMISO Sep 2022target 2029
Solar + storage project J3231, Amite County
Solar + storage
100 MWIn study Amite, MSMISO Sep 2022target 2024
Solar project J3590, Humphreys County
Solar
75.0 MWIn study Humphreys, MSMISO Apr 2024target 2028
Solar + storage project 671, Monroe County
Solar + storage
75.0 MWIn study Monroe, MSSoutheast Oct 2024target 2029
Solar project 522, Choctaw County
Solar
67.0 MWIn study Choctaw, MSSoutheast Sep 2022target 2026
Onshore wind project J3592, Sunflower County
Onshore wind
57.0 MWIn study Sunflower, MSMISO Apr 2024target 2028
Gas project 656, Benton County
Gas
54.0 MWIn study Benton, MSSoutheast Oct 2024target 2030
Gas project 25-IC-1316, Kemper County
Gas
25.0 MWIn study Kemper, MSSoutheast Apr 2025target 2027
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)