Solar + storage project 25-IC-1337, Wayne County

Solar + storage project 25-IC-1337, Wayne County is a 100 MW solar + storage request in interconnection study in the Southeast interconnection queue, in Wayne County, Mississippi, connecting to Southern Company.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25-IC-1337
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Waynesboro - Lucedale 115 kV line
Location
Wayne County, Mississippi
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
Cluster Study
Queue status
Active
Entered queue
14 April 2025
Proposed online date
August 2028

Location

Marker shows the centre of Wayne County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Other requests in Wayne County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem