United States › Grid › Interconnection queues › Arizona
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Arizona — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Ranegras Eagletail Solar |
900 MW | Withdrawn / abandoned |
| Gas project Q39, Pinal County Gas |
864 MW | Withdrawn / abandoned |
| Solar + storage project Q21, Maricopa County Solar + storage |
864 MW | Withdrawn / abandoned |
| Solar + storage project Q396, Navajo County Solar + storage |
850 MW | Withdrawn / abandoned |
| Other project 155, Cochise County Other |
800 MW | Withdrawn / abandoned |
| Solar + storage project Q27, Pinal County Solar + storage |
800 MW | Withdrawn / abandoned |
| Solar + storage project Q14, Maricopa County Solar + storage |
800 MW | Withdrawn / abandoned |
| Solar + storage project Q92, Maricopa County Solar + storage |
800 MW | Withdrawn / abandoned |
| Solar + storage project Q414, Yuma County Solar + storage |
800 MW | Withdrawn / abandoned |
| Solar project Q39, Maricopa County Solar |
800 MW | Withdrawn / abandoned |
| Solar + storage project Q2506, Navajo County Solar + storage |
786 MW | Withdrawn / abandoned |
| Solar + storage project Q403, Navajo County Solar + storage |
750 MW | Withdrawn / abandoned |
| Palomas Solar Solar |
750 MW | Withdrawn / abandoned |
| Solar + storage project Q01, Maricopa County Solar + storage |
720 MW | Withdrawn / abandoned |
| Other project Q433, Coconino County Other |
700 MW | Withdrawn / abandoned |
| CVH Power II Solar |
700 MW | Withdrawn / abandoned |
| Solar project Q17, Maricopa County Solar |
700 MW | Withdrawn / abandoned |
| Other project Q551, Coconino County Other |
700 MW | Withdrawn / abandoned |
| Other project Q512, Mohave County Other |
700 MW | Withdrawn / abandoned |
| Solar + storage project Q43, Navajo County Solar + storage |
700 MW | Withdrawn / abandoned |
| Onshore wind project Q281, Navajo County Onshore wind |
665 MW | Withdrawn / abandoned |
| Solar + storage project Q506, Maricopa County Solar + storage |
660 MW | Withdrawn / abandoned |
| Gas project Q04, Pinal County Gas |
659 MW | Withdrawn / abandoned |
| Solar + storage project Q445, Maricopa County Solar + storage |
647 MW | Withdrawn / abandoned |
| Solar + storage project Q80, Apache County Solar + storage |
643 MW | Withdrawn / abandoned |
| Other project Q219, Maricopa County Other |
634 MW | Withdrawn / abandoned |
| Solar + storage project Q87, Maricopa County Solar + storage |
630 MW | Withdrawn / abandoned |
| Other project Q173, Maricopa County Other |
620 MW | Withdrawn / abandoned |
| Papago Solar + storage |
613 MW | Withdrawn / abandoned |
| Solar + storage project Q20, Pinal County Solar + storage |
607 MW | Withdrawn / abandoned |
| Gas project Q04, Pinal County Gas |
606 MW | Withdrawn / abandoned |
| Solar + storage project Q490, Mohave County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar project Q68, Maricopa County Solar |
600 MW | Withdrawn / abandoned |
| Other project Q169, Maricopa County Other |
600 MW | Withdrawn / abandoned |
| Solar + storage project Q95, Navajo County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project Q19, Pinal County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project Q110, Navajo County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project Q2514, Navajo County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project Q48, Pinal County Solar + storage |
600 MW | Withdrawn / abandoned |
| Other project 154, Cochise County Other |
600 MW | Withdrawn / abandoned |
| Solar + storage project Q51, Pinal County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project Q67, Maricopa County Solar + storage |
600 MW | Withdrawn / abandoned |
| Gas project Q11, Maricopa County Gas |
597 MW | Withdrawn / abandoned |
| South Point Energy Center Gas |
550 MW | Withdrawn / abandoned |
| Solar project Q481, Maricopa County Solar |
550 MW | Withdrawn / abandoned |
| Gas project Q06, Pinal County Gas |
540 MW | Withdrawn / abandoned |
| Battery storage project Q24, Pinal County Battery storage |
533 MW | Withdrawn / abandoned |
| Battery storage project Q2513, Pinal County Battery storage |
529 MW | Withdrawn / abandoned |
| Arizona Mohave Solar Solar |
521 MW | Withdrawn / abandoned |
| Gas project Q02, Pinal County Gas |
520 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)