Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15918.8 GW
Active in queue18.8 GW159 requests
Agreement signed1,630 MW24 requests
Withdrawn23543.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

159 requests · page 2 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 962748, Jones County
Solar
80.0 MWIn study Jones, NCSoutheast Oct 2024
Solar project 196564, Davidson County
Solar
80.0 MWAgreement signed Davidson, NCSoutheast Jan 2022
Solar project 564510, Bladen County
Solar
80.0 MWAgreement signed Bladen, NCSoutheast Jun 2022target 2027
Other project PP00035, Wilson County
Other
80.0 MWIn study Wilson, NCSoutheast Jun 2025target 2029
Other project PP00051, Duplin County
Other
80.0 MWIn study Duplin, NCSoutheast Aug 2025target 2029
Solar project 915751, Granville County
Solar
80.0 MWIn study Granville, NCSoutheast Sep 2023
Solar project 917443, Scotland County
Solar
80.0 MWAgreement signed Scotland, NCSoutheast Sep 2023
Solar project 569890, Wayne County
Solar
80.0 MWAgreement signed Wayne, NCSoutheast Jun 2022target 2029
Other project PP00042, Granville County
Other
80.0 MWIn study Granville, NCSoutheast Jun 2025target 2027
Other project PP00044, Duplin County
Other
80.0 MWIn study Duplin, NCSoutheast Aug 2025target 2029
Solar project 569632, Scotland County
Solar
80.0 MWUnder construction Scotland, NCSoutheast Jun 2022target 2026
Solar project 948720, Nash County
Solar · Duke Energy Progress, LLC
80.0 MWUnder construction Nash, NCSoutheast Jun 2017target 2025
Solar project 977272, Wayne County
Solar
80.0 MWIn study Wayne, NCSoutheast Jun 2025
Solar project 977914, Columbus County
Solar
80.0 MWIn study Columbus, NCSoutheast Jun 2025
Solar project 962971, Duplin County
Solar
80.0 MWIn study Duplin, NCSoutheast Oct 2024
Solar project 977882, Cumberland County
Solar
74.9 MWIn study Cumberland, NCSoutheast Jun 2025
Solar project 977832, Granville County
Solar
74.9 MWIn study Granville, NCSoutheast Jun 2025
Solar project 955167, Johnston County
Solar
73.0 MWUnder construction Johnston, NCSoutheast Jun 2022target 2026
Solar project 962965, Lenoir County
Solar
70.0 MWIn study Lenoir, NCSoutheast Oct 2024
Solar project 963472, Robeson County
Solar
70.0 MWIn study Robeson, NCSoutheast Sep 2024
Other project PP00036, Robeson County
Other
70.0 MWIn study Robeson, NCSoutheast Jul 2025target 2028
Other project PP00045, Lenoir County
Other
70.0 MWIn study Lenoir, NCSoutheast Aug 2025target 2029
Solar project 920659, Wayne County
Solar
67.0 MWAgreement signed Wayne, NCSoutheast Sep 2023
Other project PP00037, Wayne County
Other
67.0 MWIn study Wayne, NCSoutheast Jul 2025target 2029
Other project PP00050, Cumberland County
Other
65.0 MWIn study Cumberland, NCSoutheast Sep 2025target 2029
Solar project 963044, Cumberland County
Solar · Duke Energy Progress LLC
65.0 MWIn study Cumberland, NCSoutheast Sep 2024
Battery storage project 566170, Wake County
Battery storage · Duke Energy Progress, LLC
56.0 MWAgreement signed Wake, NCSoutheast Jun 2022target 2026
Battery storage project 956218, Nash County
Battery storage · Duke Energy Progress LLC
50.0 MWIn study Nash, NCSoutheast Jun 2024
Other project PP00038, Nash County
Other
50.0 MWIn study Nash, NCSoutheast Jul 2025target 2029
Battery storage project 186466, Gaston County
Battery storage
50.0 MWUnder construction Gaston, NCSoutheast Jul 2021target 2025
Solar project 977831, Hoke County
Solar
49.9 MWIn study Hoke, NCSoutheast Jun 2025
Gas project 899591, Richmond County
Gas · Duke Energy Progress, LLC
46.8 MWAgreement signed Richmond, NCSoutheast Jun 2023
Gas project PP00013, Richmond County
Gas
46.8 MWAgreement signed Richmond, NCSoutheast Apr 2025target 2025
Solar project 920663, Randolph County
Solar
44.0 MWIn study Randolph, NCSoutheast Sep 2023
Nuclear project 957247, Mecklenburg County
Nuclear
40.0 MWIn study Mecklenburg, NCSoutheast Jun 2024
Solar project 919551, Lincoln County
Solar
40.0 MWAgreement signed Lincoln, NCSoutheast Sep 2023
Gas project 957700, Richmond County
Gas · Duke Energy Progress LLC
35.0 MWIn study Richmond, NCSoutheast Jun 2024
Solar project 126062, Alamance County
Solar
35.0 MWAgreement signed Alamance, NCSoutheast Mar 2020target 2026
Gas project PP00014, Richmond County
Gas
35.0 MWIn study Richmond, NCSoutheast Apr 2025target 2026
Gas project 957510, Rockingham County
Gas
33.0 MWIn study Rockingham, NCSoutheast Jun 2024
Gas project 957509, Rockingham County
Gas
33.0 MWIn study Rockingham, NCSoutheast Jun 2024
Nuclear project 957243, Mecklenburg County
Nuclear
33.0 MWIn study Mecklenburg, NCSoutheast Jun 2024
Gas project 957511, Rockingham County
Gas
33.0 MWIn study Rockingham, NCSoutheast Jun 2024
Gas project 957447, Rockingham County
Gas
33.0 MWIn study Rockingham, NCSoutheast Jun 2024
Gas project 957437, Rockingham County
Gas
33.0 MWIn study Rockingham, NCSoutheast Jun 2024
Other project 897247, Johnston County
Other
30.5 MWUnder construction Johnston, NCSoutheast Jun 2023target 2026
Battery storage project 191894, Buncombe County
Battery storage · Duke Energy Progress, LLC
30.5 MWUnder construction Buncombe, NCSoutheast Aug 2021target 2026
Coal project 978035, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Coal project 978034, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Gas project 956971, Rowan County
Gas
28.0 MWIn study Rowan, NCSoutheast Jun 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)