NUCLEAR · SOUTHEASTNuclear project 957243, Mecklenburg County
Nuclear project 957243, Mecklenburg County is a 33.0 MW nuclear request in interconnection study in the Southeast interconnection queue, in Mecklenburg County, North Carolina, connecting to Duke Energy Carolinas.
- PlanningQueued Jun 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 957243
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Carolinas
- Connection point (POI)
- MCGUIRE SWITCHING STA
- Location
- Mecklenburg County, North Carolina
- Technology
- Nuclear: 33.0 MW
- Total requested
- 33.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Phase 3 Cluster Study - Study Complete
- Queue status
- Active
- Entered queue
- 26 June 2024
Location
Marker shows the centre of Mecklenburg County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Mecklenburg County
- Battery storage project 567168, Mecklenburg CountyBattery storage · 197 MW · in study
- Nuclear project 957247, Mecklenburg CountyNuclear · 40.0 MW · in study
- Battery storage project 976447, Mecklenburg CountyBattery storage · 4.1 MW · in study
- Battery storage project 41456, Mecklenburg CountyBattery storage · 2.8 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem