United States › Grid › Interconnection queues › Pennsylvania

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Pennsylvania — page 19

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,354164.3 GW
Active in queue12.5 GW231 requests
Agreement signed2,306 MW58 requests
Withdrawn1,354164.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,354 requests · page 19 of 28
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AH1-631, Crawford County
Battery storage
15.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2021target 2023
Orrtanna
Battery storage
15.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2020target 2027
Big Pond Solar Power Plant
Solar
15.0 MWWithdrawn / abandoned Bradford, PAPJM Mar 2020target 2022
Gas project AF1-197, Allegheny County
Gas
15.0 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2019target 2019
Solar project AG1-392C, Potter County
Solar · PO-Cowburn LLC
15.0 MWWithdrawn / abandoned Potter, PAPJM Oct 2020target 2022
Hydro project U1-071, Allegheny County
Hydro
15.0 MWWithdrawn / abandoned Allegheny, PAPJM Apr 2008target 2015
Solar project AH1-629, York County
Solar
15.0 MWWithdrawn / abandoned York, PAPJM Sep 2021target 2023
Battery storage project AH1-475, Crawford County
Battery storage
15.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2021target 2023
Solar project AF1-218, Somerset County
Solar
15.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2019target 2020
Battery storage project AD2-128, Fayette County
Battery storage
15.0 MWWithdrawn / abandoned Fayette, PAPJM Mar 2018target 2020
Richardson Solar
Solar
15.0 MWWithdrawn / abandoned Clarion, PAPJM Mar 2020target 2027
Palmyra Solar
Solar
15.0 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2019target 2027
Solar project AH2-017, Somerset County
Solar
15.0 MWWithdrawn / abandoned Somerset, PAPJM Oct 2021target 2023
Solar project W1-046, Lancaster County
Solar
15.0 MWWithdrawn / abandoned Lancaster, PAPJM Mar 2010target 2015
Solar project W3-102, Wayne County
Solar
15.0 MWWithdrawn / abandoned Wayne, PAPJM Oct 2010target 2011
Solar project AF1-241, Adams County
Solar
15.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2019target 2022
Solar project AH1-470, Northumberland County
Solar
15.0 MWWithdrawn / abandoned Northumberland, PAPJM Sep 2021target 2023
Solar project AI1-063, Bedford County
Solar
15.0 MWWithdrawn / abandoned Bedford, PAPJM Jun 2022target 2027
Pearl Solar
Solar
15.0 MWWithdrawn / abandoned Venango, PAPJM Mar 2020target 2026
Solar project W3-166, Chester County
Solar
15.0 MWWithdrawn / abandoned Chester, PAPJM Oct 2010target 2011
East Ridge Solar
Solar
15.0 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2019target 2027
Solar project AB1-129, Franklin County
Solar
15.0 MWWithdrawn / abandoned Franklin, PAPJM Oct 2015target 2017
Solar project W3-168, Adams County
Solar
15.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2010target 2012
Battery storage project AH1-468, York County
Battery storage
15.0 MWWithdrawn / abandoned York, PAPJM Sep 2021target 2023
Solar project AG2-201, Clarion County
Solar
15.0 MWWithdrawn / abandoned Clarion, PAPJM Mar 2021target 2023
Bellegrove Solar
Solar
15.0 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2019target 2027
Centre Hall
Solar
15.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2026
Solar project AD2-117, Berks County
Solar
15.0 MWWithdrawn / abandoned Berks, PAPJM Mar 2018target 2020
Solar + storage project AH1-469, Montour County
Solar + storage
15.0 MWWithdrawn / abandoned Montour, PAPJM Sep 2021target 2023
Solar project AF1-095, Clearfield County
Solar
15.0 MWWithdrawn / abandoned Clearfield, PAPJM Aug 2019target 2023
Solar project AG2-425, Cambria County
Solar
15.0 MWWithdrawn / abandoned Cambria, PAPJM Mar 2021target 2023
Solar project AG2-654, Armstrong County
Solar · IMG Solar LLC
14.7 MWWithdrawn / abandoned Armstrong, PAPJM Jan 2025target 2022
Brunner Island #1
Coal
14.0 MWWithdrawn / abandoned York, PAPJM Feb 2001target 2002
Brunner Island #2
Coal
14.0 MWWithdrawn / abandoned York, PAPJM Feb 2001target 2002
Solar project AG2-090, Somerset County
Solar · Neptune Solar LLC
14.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2025target 2023
Hydro project U1-070, Allegheny County
Hydro
14.0 MWWithdrawn / abandoned Allegheny, PAPJM Apr 2008target 2015
Onshore wind project K12, Somerset County
Onshore wind
13.6 MWWithdrawn / abandoned Somerset, PAPJM Jul 2003target 2005
Solar project AF1-286, Bradford County
Solar
13.6 MWWithdrawn / abandoned Bradford, PAPJM Sep 2019target 2026
Solar project AF2-148, Huntingdon County
Solar
13.5 MWWithdrawn / abandoned Huntingdon, PAPJM Mar 2020target 2023
Gas project C16, Clearfield County
Gas
13.5 MWWithdrawn / abandoned Clearfield, PAPJM Mar 2000
Solar project AF1-255, Bedford County
Solar
13.5 MWWithdrawn / abandoned Bedford, PAPJM Sep 2019target 2019
Solar project AF2-147, Mifflin County
Solar
13.1 MWWithdrawn / abandoned Mifflin, PAPJM Mar 2020target 2023
Solar project AI1-036, Somerset County
Solar
13.0 MWWithdrawn / abandoned Somerset, PAPJM Apr 2022target 2028
Solar project AH1-371, Allegheny County
Solar
13.0 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2021target 2024
Solar project V4-077, Mifflin County
Solar
13.0 MWWithdrawn / abandoned Mifflin, PAPJM Jan 2010target 2014
Solar project AG2-142, Columbia County
Solar
13.0 MWWithdrawn / abandoned Columbia, PAPJM Feb 2021target 2023
Solar project AH1-373, Greene County
Solar
12.8 MWWithdrawn / abandoned Greene, PAPJM Sep 2021target 2024
Solar project AG2-060, Luzerne County
Solar
12.6 MWWithdrawn / abandoned Luzerne, PAPJM Dec 2020target 2022
IntelliWatt
Other
12.5 MWWithdrawn / abandoned Northumberland, PAPJM May 2007target 2012
Battery storage project AB1-114, Mercer County
Battery storage
12.5 MWWithdrawn / abandoned Mercer, PAPJM Oct 2015target 2017
Page 19 of 28

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)