United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
COAL Β· PJMBrunner Island #2
Brunner Island #2 is a 14.0 MW coal request withdrawn in the PJM interconnection queue, in York County, Pennsylvania, connecting to PPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2001 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G04
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Brunner Island #2
- Location
- York County, Pennsylvania
- Technology
- Coal: 14.0 MW
- Total requested
- 14.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 23 February 2001
- Proposed online date
- January 2002
Location
Marker shows the centre of York County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in York County
- Peach Bottom Units #2 & #3Nuclear Β· 44.0 MW Β· agreement signed
- Battery storage project AH2-335, York CountyBattery storage Β· 130 MW Β· in study
- Strinestown Solar ProjectSolar Β· 79.6 MW Β· suspended
- Dover SolarSolar Β· 55.0 MW Β· suspended
- Dover SolarSolar Β· 20.0 MW Β· suspended
- Delta YorkGas Β· 760 MW Β· built
- DeltaGas Β· 550 MW Β· built
- Peach Bottom Units 2 & 3Nuclear Β· 206 MW Β· built
- Muddy RunHydro Β· 160 MW Β· built
- Peach Bottom - Units 2 & 3Nuclear Β· 140 MW Β· built
- Delta YorkGas Β· 120 MW Β· built
- Peach Bottom 2 & 3Nuclear Β· 70.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem