πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AG2-090, Somerset County

Solar project AG2-090, Somerset County is a 14.0 MW solar request withdrawn in the PJM interconnection queue, in Somerset County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-090
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Developer
Neptune Solar LLC
Connection point (POI)
Scalp Level 23 kV IV
Location
Somerset County, Pennsylvania
Technology
Solar: 14.0 MW
Total requested
14.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
11 March 2025
Proposed online date
January 2023
Withdrawn
December 2025

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem