United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 18

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 18 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 164, Rosebud County
Onshore wind
301 MWWithdrawn / abandoned Rosebud, MTWest Sep 2013target 2021
Onshore wind project 163, Rosebud County
Onshore wind
301 MWWithdrawn / abandoned Rosebud, MTWest Jul 2013target 2016
Onshore wind project 379, Rosebud County
Onshore wind
301 MWWithdrawn / abandoned Rosebud, MTWest Jun 2020target 2022
Battery storage project C3-167, San Juan County
Battery storage
300 MWWithdrawn / abandoned San Juan, UTWest May 2023target 2026
Onshore wind project 2007-G7
Onshore wind
300 MWWithdrawn / abandoned West Jul 2007target 2012
Solar project GI-2017-31, Pueblo County
Solar
300 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2019
Solar project Q43, Kern County
Solar
300 MWWithdrawn / abandoned Kern, CAWest Jun 2013target 2016
Solar project Q56, Inyo County
Solar
300 MWWithdrawn / abandoned Inyo, CAWest Sep 2016target 2020
Solar + storage project 429, Cascade County
Solar + storage
300 MWWithdrawn / abandoned Cascade, MTWest Jun 2022target 2025
Onshore wind project G0982, Sherman County
Onshore wind
300 MWWithdrawn / abandoned Sherman, ORWest Nov 2023target 2028
Wind + storage project C3-022, Sweetwater County
Wind + storage
300 MWWithdrawn / abandoned Sweetwater, WYWest May 2023target 2027
Onshore wind project G0272, Yakima County
Onshore wind
300 MWWithdrawn / abandoned Yakima, WAWest May 2007target 2008
Battery storage project C2-16, Carbon County
Battery storage · PacifiCorp
300 MWWithdrawn / abandoned Carbon, UTWest Apr 2022target 2028
Wind + storage project CLPT G28, Converse County
Wind + storage
300 MWWithdrawn / abandoned Converse, WYWest Jan 2024target 2026
Onshore wind project G0860, Lincoln County
Onshore wind
300 MWWithdrawn / abandoned Lincoln, WAWest Apr 2023target 2027
Solar + storage project Q513, Yuma County
Solar + storage
300 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2026
Solar + storage project PIS036, Klamath County
Solar + storage
300 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2026
Solar + storage project C1-47, Iron County
Solar + storage
300 MWWithdrawn / abandoned Iron, UTWest May 2021target 2025
Onshore wind project GI-2010-16, Kit Carson County
Onshore wind
300 MWWithdrawn / abandoned Kit Carson, COWest Nov 2010target 2014
Solar + storage project C3-133, Box Elder County
Solar + storage
300 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2027
Solar + storage project Q516, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2023target 2027
Solar + storage project Q69, San Bernardino County
Solar + storage
300 MWWithdrawn / abandoned San Bernardino, CAWest Apr 2019target 2022
Solar + storage project Company OH, Lander County
Solar + storage
300 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2028
Solar project 534, Jerome County
Solar
300 MWWithdrawn / abandoned Jerome, IDWest May 2018
Solar + storage project Company 188, Clark County
Solar + storage
300 MWWithdrawn / abandoned Clark, NVWest Sep 2019target 2022
Solar + storage project 658, Power County
Solar + storage
300 MWWithdrawn / abandoned Power, IDWest Jun 2022target 2024
Gas project 24, Lane County
Gas
300 MWWithdrawn / abandoned Lane, ORWest Jun 2003target 2007
Solar + storage project C4-039, Franklin County
Solar + storage
300 MWWithdrawn / abandoned Franklin, IDWest May 2024target 2028
Solar + storage project 1171, Converse County
Solar + storage
300 MWWithdrawn / abandoned Converse, WYWest Oct 2019target 2021
Onshore wind project 168, Cochise County
Onshore wind
300 MWWithdrawn / abandoned Cochise, AZWest Apr 2024target 2030
Onshore wind project PIS029, Utah County
Onshore wind
300 MWWithdrawn / abandoned Utah, UTWest Mar 2023target 2027
Cedar Hills Energy LLC
Gas · Cedar Hills Energy LLC
300 MWWithdrawn / abandoned King, WAWest May 2001target 2004
Solar + storage project C4-111, Iron County
Solar + storage
300 MWWithdrawn / abandoned Iron, UTWest May 2024target 2029
Onshore wind project GI-2010-3, Huerfano County
Onshore wind
300 MWWithdrawn / abandoned Huerfano, COWest Feb 2010target 2013
Battery storage project Company 199, Clark County
Battery storage
300 MWWithdrawn / abandoned Clark, NVWest Sep 2021target 2025
Onshore wind project GI-2007-4, Weld County
Onshore wind
300 MWWithdrawn / abandoned Weld, COWest Mar 2007target 2013
Battery storage project C3-048, Clark County
Battery storage · PacifiCorp
300 MWWithdrawn / abandoned Clark, WAWest May 2023target 2030
Solar project Q29, Clark County
Solar
300 MWWithdrawn / abandoned Clark, NVWest Jun 2012target 2014
Solar project Q69, La Paz County
Solar
300 MWWithdrawn / abandoned La Paz, AZWest Jun 2009target 2015
Onshore wind project G0427, Wheeler County
Onshore wind
300 MWWithdrawn / abandoned Wheeler, ORWest Apr 2010target 2013
Battery storage project Q399, Coconino County
Battery storage
300 MWWithdrawn / abandoned Coconino, AZWest Sep 2021target 2023
Onshore wind project Q381, Pinal County
Onshore wind
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2021target 2024
Onshore wind project 928, Platte County
Onshore wind
300 MWWithdrawn / abandoned Platte, WYWest Aug 2017target 2020
Onshore wind project G0727, Garfield County
Onshore wind
300 MWWithdrawn / abandoned Garfield, WAWest Feb 2022target 2026
Onshore wind project 46, Lincoln County
Onshore wind
300 MWWithdrawn / abandoned Lincoln, WYWest Sep 2004target 2006
Solar + storage project C3-030, Klamath County
Solar + storage
300 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2027
Wind + storage project C3-023, Sweetwater County
Wind + storage
300 MWWithdrawn / abandoned Sweetwater, WYWest May 2023target 2027
Solar + storage project Company QB, Pershing County
Solar + storage
300 MWWithdrawn / abandoned Pershing, NVWest Mar 2023target 2027
Solar + storage project 1199, Power County
Solar + storage
300 MWWithdrawn / abandoned Power, IDWest Mar 2020target 2023
Same as project below
Onshore wind
300 MWWithdrawn / abandoned Socorro, NMWest Apr 2010target 2013
Page 18 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)