๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2021 requests) โ€” page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,149339.1 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,149 requests ยท page 17 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 21-11154, Larimer County
Solar + storage
125 MWWithdrawn / abandoned Larimer, COWest Nov 2021target 2025
Battery storage project 122, Kitsap County
Battery storage
125 MWWithdrawn / abandoned Kitsap, WAWest Aug 2021target 2024
Solar project J1920, Leelanau County
Solar
125 MWWithdrawn / abandoned Leelanau, MIMISO Aug 2021target 2023
Solar project J1921, Montcalm County
Solar
125 MWWithdrawn / abandoned Montcalm, MIMISO Aug 2021target 2023
Onshore wind project 21-11156, Larimer County
Onshore wind
125 MWWithdrawn / abandoned Larimer, COWest Nov 2021target 2025
Battery storage project AG2-359, Brown County
Battery storage
125 MWWithdrawn / abandoned Brown, OHPJM Mar 2021target 2024
Solar + storage project AH1-368, Bedford County
Solar + storage
125 MWWithdrawn / abandoned Bedford, VAPJM Sep 2021target 2023
Solar project 162
Solar
125 MWWithdrawn / abandoned SCSoutheast Jun 2021
Solar + storage project 21-11155, Larimer County
Solar + storage
125 MWWithdrawn / abandoned Larimer, COWest Nov 2021target 2025
Honey Ridge Solar
Solar + storage ยท Honey Ridge Solar 1, LLC
125 MWWithdrawn / abandoned Jefferson, NYNYISO Feb 2021
Solar project AG2-312, City Of Suffolk County
Solar
125 MWWithdrawn / abandoned City Of Suffolk, VAPJM Mar 2021target 2025
Onshore wind project J1866, Clark County
Onshore wind
125 MWWithdrawn / abandoned Clark, WIMISO Aug 2021target 2024
Solar + storage project J2118, Monroe County
Solar + storage
125 MWWithdrawn / abandoned Monroe, MIMISO Sep 2021target 2025
Battery storage project AH1-596, Benton County
Battery storage
125 MWWithdrawn / abandoned Benton, INPJM Sep 2021target 2025
Solar project AH1-041, Jay County
Solar ยท ACE Development Company, LLC
125 MWWithdrawn / abandoned Jay, INPJM Jun 2021target 2025
Battery storage project AG2-689
Battery storage
125 MWWithdrawn / abandoned WVPJM Mar 2021target 2024
Solar project AG2-633, Lunenburg County
Solar
125 MWWithdrawn / abandoned Lunenburg, VAPJM Mar 2021target 2025
Solar project 168, Marlboro County
Solar
125 MWWithdrawn / abandoned Marlboro, SCSoutheast Oct 2021
Red Diamond Solar
Solar + storage
124 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2028
Normandy
Solar + storage
122 MWWithdrawn / abandoned Kings, CACAISO Apr 2021target 2024
Solar project J1988, Coahoma County
Solar
121 MWWithdrawn / abandoned Coahoma, MSMISO Nov 2021target 2025
Solar + storage project 475, Lowndes County
Solar + storage
120 MWWithdrawn / abandoned Lowndes, MSSoutheast Apr 2021
Battery storage project G0720, Powell County
Battery storage
120 MWWithdrawn / abandoned Powell, MTWest Dec 2021target 2024
Solar project AH1-520, Union County
Solar
120 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2024
Solar project J2240, Nevada County
Solar
120 MWWithdrawn / abandoned Nevada, ARMISO Dec 2021target 2024
Solar project 170, Williamsburg County
Solar
120 MWWithdrawn / abandoned Williamsburg, SCSoutheast Oct 2021
Solar project AH1-267, King And Queen County
Solar
120 MWWithdrawn / abandoned King And Queen, VAPJM Sep 2021target 2025
Solar + storage project IC-996, Charlton County
Solar + storage
120 MWWithdrawn / abandoned Charlton, GASoutheast Nov 2021target 2026
Solar project J2030, Isanti County
Solar
120 MWWithdrawn / abandoned Isanti, MNMISO Jul 2021target 2024
Solar project AH1-621, Allegany County
Solar
120 MWWithdrawn / abandoned Allegany, MDPJM Sep 2021target 2025
Solar project AH1-605, Union County
Solar
120 MWWithdrawn / abandoned Union, INPJM Sep 2021target 2025
Solar + storage project AG2-517, Rock Island County
Solar + storage
120 MWWithdrawn / abandoned Rock Island, ILPJM Mar 2021target 2023
Solar project AG2-678, Knott County
Solar
120 MWWithdrawn / abandoned Knott, KYPJM Mar 2021target 2024
Cold Creek Solar
Solar + storage ยท Northland Power U.S. Projects
120 MWWithdrawn / abandoned Allegany, NYNYISO Jun 2021
Solar project AG2-136, Fayette County
Solar
120 MWWithdrawn / abandoned Fayette, PAPJM Feb 2021target 2023
Solar project AH1-607, Delaware County
Solar
119 MWWithdrawn / abandoned Delaware, INPJM Sep 2021target 2025
Onshore wind project 2021-G5
Onshore wind
119 MWWithdrawn / abandoned West Nov 2021target 2023
Solar project AH1-524, Laporte County
Solar
117 MWWithdrawn / abandoned Laporte, INPJM Sep 2021target 2025
Battery storage project Q85, Maricopa County
Battery storage
117 MWWithdrawn / abandoned Maricopa, AZWest Oct 2021target 2025
Union Energy Center, LLC
Battery storage ยท Union Energy Center, LLC
116 MWWithdrawn / abandoned Putnam, NYNYISO May 2021
Solar project J1652, Champaign County
Solar
116 MWWithdrawn / abandoned Champaign, ILMISO Dec 2021target 2023
Solar project AH1-226, City Of Emporia County
Solar ยท Virginia Electric and Power Company
115 MWWithdrawn / abandoned City Of Emporia, VAPJM Sep 2021target 2025
Solar + storage project 611, Elmore County
Solar + storage
115 MWWithdrawn / abandoned Elmore, IDWest Jul 2021
Ruby Storage Project
Battery storage ยท Hanwha Q CELLS USA
115 MWWithdrawn / abandoned Ontario, NYNYISO Sep 2021
Solar project J2112, Hardin County
Solar
115 MWWithdrawn / abandoned Hardin, TXMISO Dec 2021target 2024
Geothermal project C1-05, Millard County
Geothermal
115 MWWithdrawn / abandoned Millard, UTWest Apr 2021target 2026
Battery storage project AG2-225, Anne Arundel County
Battery storage
115 MWWithdrawn / abandoned Anne Arundel, MDPJM Mar 2021target 2022
Solar project AG2-467, Logan County
Solar ยท Invenergy Solar Project Development LLC
115 MWWithdrawn / abandoned Logan, ILPJM Mar 2021target 2025
Solar project AH1-484, Henry County
Solar
115 MWWithdrawn / abandoned Henry, INPJM Sep 2021target 2023
Solar + storage project AH1-388, Mecklenburg County
Solar + storage
115 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)