Queue requests in study in West (non-ISO utilities) — page 16

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,496455.6 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,496 requests · page 16 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Q409, Maricopa County
Battery storage
200 MWIn study Maricopa, AZWest Sep 2021target 2025
Battery storage project Company 202, Clark County
Battery storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Solar + storage project IA-PNM-2023-22, Santa Fe County
Solar + storage
200 MWIn study Santa Fe, NMWest Sep 2023target 2028
Battery storage project 23-239, Multnomah County
Battery storage
200 MWIn study Multnomah, ORWest Dec 2023target 2028
Battery storage project Q291, Maricopa County
Battery storage
200 MWIn study Maricopa, AZWest Sep 2018target 2023
Solar + storage project 2024-G8, Clark County
Solar + storage
200 MWIn study Clark, NVWest Dec 2024target 2028
Onshore wind project 11-040, Gilliam County
Onshore wind
200 MWPaused / redesign Gilliam, ORWest Mar 2011target 2015
Onshore wind project 09-033, Wasco County
Onshore wind
200 MWPaused / redesign Wasco, ORWest Jan 2009target 2013
Battery storage project 149, Whatcom County
Battery storage
200 MWIn study Whatcom, WAWest Apr 2024target 2027
Solar + storage project Company LZ, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Other project Q585, Maricopa County
Other
200 MWIn study Maricopa, AZWest May 2025target 2030
Solar + storage project Company MK, Lyon County
Solar + storage
200 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Battery storage project GI-RSC-2025-02, Moffat County
Battery storage
200 MWIn study Moffat, COWest Jul 2025target 2029
Other project 110, Pima County
Other · TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Solar + storage project Q355, Maricopa County
Solar + storage
200 MWPaused / redesign Maricopa, AZWest Sep 2020target 2023
Battery storage project GI-SISS-2025-03, Mckinley County
Battery storage
200 MWIn study Mckinley, NMWest Jul 2025target 2027
Solar project 3RSC-2023-01, Pueblo County
Solar
200 MWIn study Pueblo, COWest May 2023target 2025
Solar + storage project Company OB, Churchill County
Solar + storage
200 MWPaused / redesign Churchill, NVWest Sep 2022target 2030
Solar project 5RSC-2024-23, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jan 2024target 2028
Solar + storage project 710, Ada County
Solar + storage
200 MWIn study Ada, IDWest Mar 2023target 2026
Other project Q605, Maricopa County
Other
200 MWIn study Maricopa, AZWest May 2025target 2031
Battery storage project GI-2011-2 & 7, Arapahoe County
Battery storage
200 MWPaused / redesign Arapahoe, COWest Sep 2022target 2025
Onshore wind project CS25-15, Spokane County
Onshore wind
200 MWIn study Spokane, WAWest Apr 2025target 2030
Onshore wind project CS25-17, Spokane County
Onshore wind
200 MWIn study Spokane, WAWest Apr 2025target 2030
Onshore wind project 360, Wheatland County
Onshore wind
200 MWPaused / redesign Wheatland, MTWest Feb 2019target 2021
Onshore wind project 120, Cochise County
Onshore wind
200 MWIn study Cochise, AZWest May 2022target 2025
Solar + storage project G0694, Crook County
Solar + storage
200 MWIn study Crook, ORWest Sep 2021target 2025
Battery storage project SC1Q32, Sacramento County
Battery storage
200 MWIn study Sacramento, CAWest Jul 2025target 2031
Onshore wind project NVE
Onshore wind
200 MWIn study NVWest target 2014
Solar + storage project Q225, Maricopa County
Solar + storage
200 MWIn study Maricopa, AZWest Sep 2014target 2021
Gas project S0021, Utah County
Gas
200 MWIn study Utah, UTWest Oct 2023target 2025
Other project Q604, Pinal County
Other
200 MWIn study Pinal, AZWest May 2025target 2030
Solar project 7, Grant County
Solar
200 MWIn study Grant, WAWest Sep 2020
Solar + storage project Company OJ, Esmeralda County
Solar + storage
200 MWIn study Esmeralda, NVWest Jan 2023target 2026
Gas project 07-029, Marion County
Gas
200 MWPaused / redesign Marion, ORWest Oct 2007target 2011
Gas project 07-027, Clackamas County
Gas
200 MWPaused / redesign Clackamas, ORWest Oct 2007target 2011
Solar + storage project Q288, Maricopa County
Solar + storage
200 MWIn study Maricopa, AZWest Sep 2018target 2021
Solar + storage project IA-PNM-2023-04, Bernalillo County
Solar + storage
200 MWIn study Bernalillo, NMWest Jan 2023target 2027
Other project 38412, Goshen County
Other
200 MWIn study Goshen, WYWest Jul 2025target 2029
Battery storage project 11, Sacramento County
Battery storage
200 MWIn study Sacramento, CAWest Apr 2021target 2026
Battery storage project IA-PNM-2023-02, Sandoval County
Battery storage
200 MWIn study Sandoval, NMWest Jan 2023target 2027
Solar + storage project Company QC, Pershing County
Solar + storage
200 MWIn study Pershing, NVWest Mar 2023target 2026
Battery storage project 100, Pierce County
Battery storage
200 MWPaused / redesign Pierce, WAWest Apr 2021target 2028
Solar project 8, Grant County
Solar
200 MWIn study Grant, WAWest Jul 2022
Onshore wind project 1 Pre Jan 2004, Kittitas County
Onshore wind
200 MWIn study Kittitas, WAWest Feb 2003target 2004
Solar + storage project Q425, Yuma County
Solar + storage
200 MWIn study Yuma, AZWest Sep 2021target 2024
Onshore wind project GI-2016-15, Lincoln County
Onshore wind
200 MWPaused / redesign Lincoln, COWest Jul 2016target 2020
Battery storage project G0889, Lane County
Battery storage
200 MWIn study Lane, ORWest Jun 2023target 2030
Solar project BHCT G49, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jun 2024target 2026
Solar + storage project 99, Franklin County
Solar + storage
200 MWIn study Franklin, WAWest Sep 2019target 2021
Page 16 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)