United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2018 requests) โ€” page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,424226.5 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,424 requests ยท page 15 of 29
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 78, Colleton County
Solar
100 MWWithdrawn / abandoned Colleton, SCSoutheast Jan 2018target 2019
Solar + storage project 1051, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2021
Solar project 99, Kershaw County
Solar
100 MWWithdrawn / abandoned Kershaw, SCSoutheast Apr 2018target 2020
Solar + storage project Company IS, Douglas County
Solar + storage
100 MWWithdrawn / abandoned Douglas, NVWest Sep 2018target 2022
White Creek Solar
Solar ยท White Creek Solar LLC
100 MWWithdrawn / abandoned Livingston, NYNYISO Jul 2018
Battery storage project Company IN, Washoe County
Battery storage
100 MWWithdrawn / abandoned Washoe, NVWest Mar 2018target 2021
Solar project J994, Callaway County
Solar
100 MWWithdrawn / abandoned Callaway, MOMISO Mar 2018target 2023
Solar project GEN-2018-019, Yoakum County
Solar
100 MWWithdrawn / abandoned Yoakum, TXSPP May 2018target 2020
Solar project IC-690, Jones County
Solar
100 MWWithdrawn / abandoned Jones, MSSoutheast Mar 2018
Solar project 77, Dorchester County
Solar
100 MWWithdrawn / abandoned Dorchester, SCSoutheast Jan 2018target 2019
Solar + storage project 1024, Cache County
Solar + storage
100 MWWithdrawn / abandoned Cache, UTWest May 2018target 2020
Solar project Company 162, Clark County
Solar
99.0 MWWithdrawn / abandoned Clark, NVWest Mar 2018target 2021
Onshore wind project J1080, Dewitt County
Onshore wind
99.0 MWWithdrawn / abandoned Dewitt, ILMISO Mar 2018target 2020
Onshore wind project AE1-233, Dekalb County
Onshore wind
97.5 MWWithdrawn / abandoned Dekalb, ILPJM Sep 2018target 2021
Mercer County Solar Project
Solar
95.0 MWWithdrawn / abandoned Mercer, KYPJM Mar 2018target 2023
Solar project TCS-06, Adams County
Solar
94.0 MWWithdrawn / abandoned Adams, WAWest Dec 2018target 2020
Solar project AD2-123, Person County
Solar
94.0 MWWithdrawn / abandoned Person, NCPJM Mar 2018target 2021
Solar + storage project XX, Columbia County
Solar + storage
91.8 MWWithdrawn / abandoned Columbia, WAWest Aug 2018target 2022
Solar project J1090, Ingham County
Solar
90.0 MWWithdrawn / abandoned Ingham, MIMISO Mar 2018target 2021
Goldenrod Solar
Solar ยท Granada Solar, LLC (Conti)
90.0 MWWithdrawn / abandoned Herkimer, NYNYISO Aug 2018
Antlers Road Solar
Solar ยท RWE Solar Development, LLC
90.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2018target 2021
Battery storage project AD2-126, Tucker County
Battery storage
90.0 MWWithdrawn / abandoned Tucker, WVPJM Mar 2018target 2020
Wind
Onshore wind
89.7 MWWithdrawn / abandoned Somerset, MEISO-NE Apr 2018target 2020
Gas project Company 164, Clark County
Gas
87.0 MWWithdrawn / abandoned Clark, NVWest Sep 2018target 2020
Solar project IC-724, Mitchell County
Solar
85.0 MWWithdrawn / abandoned Mitchell, GASoutheast Jul 2018
Solar project AE1-132, Fulton County
Solar
85.0 MWWithdrawn / abandoned Fulton, PAPJM Sep 2018target 2021
Solar project AE1-246, Barren County
Solar
85.0 MWWithdrawn / abandoned Barren, KYPJM Sep 2018target 2022
Solar project J1113, Sunflower County
Solar
85.0 MWWithdrawn / abandoned Sunflower, MSMISO Mar 2018target 2022
Solar project AE1-169, Venango County
Solar
85.0 MWWithdrawn / abandoned Venango, PAPJM Sep 2018target 2021
Solar project IC-729, Wayne County
Solar
85.0 MWWithdrawn / abandoned Wayne, GASoutheast Aug 2018
Solar project AE1-109A, Southampton County
Solar
85.0 MWWithdrawn / abandoned Southampton, VAPJM Sep 2018target 2022
Round Hill Solar
Solar
83.0 MWWithdrawn / abandoned Augusta, VAPJM Aug 2018target 2023
Dusky Storage
Other ยท Cypress Creek Renewables
83.0 MWWithdrawn / abandoned Hill, TXERCOT Jun 2018target 2020
Solar project AE1-130, Bedford County
Solar
83.0 MWWithdrawn / abandoned Bedford, VAPJM Sep 2018target 2020
Other project AE1-184, Livingston County
Other
82.7 MWWithdrawn / abandoned Livingston, ILPJM Sep 2018target 2022
Hydaspes
Solar + storage
82.0 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2018target 2022
Solar project J1023, Mississippi County
Solar
82.0 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2018target 2021
Solar project IC-671, Evans County
Solar
80.0 MWWithdrawn / abandoned Evans, GASoutheast Jan 2018
Solar + storage project 537, Harney County
Solar + storage
80.0 MWWithdrawn / abandoned Harney, ORWest Jun 2018
Solar project AD2-046, Mecklenburg County
Solar
80.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Jan 2018target 2021
Solar project 20318, Onslow County
Solar
80.0 MWWithdrawn / abandoned Onslow, NCSoutheast Oct 2018
Solar project IC-675, Geneva County
Solar
80.0 MWWithdrawn / abandoned Geneva, ALSoutheast Mar 2018
Solar project J1014, Jackson County
Solar
80.0 MWWithdrawn / abandoned Jackson, MIMISO Mar 2018target 2021
Solar project GI-2018-20, Weld County
Solar
80.0 MWWithdrawn / abandoned Weld, COWest May 2018target 2020
Solar + storage project 1033, Harney County
Solar + storage
80.0 MWWithdrawn / abandoned Harney, ORWest May 2018target 2020
Solar + storage project AE1-026, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM May 2018target 2022
Solar project IC-750, Perry County
Solar
80.0 MWWithdrawn / abandoned Perry, ALSoutheast Oct 2018
Solar + storage project AD2-184, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM Mar 2018target 2020
Solar project 20841, Craven County
Solar ยท Masked
80.0 MWWithdrawn / abandoned Craven, NCSoutheast Apr 2018
Solar project IC-746, Escambia County
Solar
80.0 MWWithdrawn / abandoned Escambia, ALSoutheast Oct 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)