πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2018-019, Yoakum County

Solar project GEN-2018-019, Yoakum County is a 100 MW solar request withdrawn in the SPP interconnection queue, in Yoakum County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2018 (completed)
  2. Withdrawn / abandonedJun 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-019
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap onto the Cochran to Lehman line at 115kV
Location
Yoakum County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
16 May 2018
Proposed online date
December 2020
Withdrawn
June 2019

Location

Marker shows the centre of Yoakum County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Yoakum County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem