United States › Grid › Interconnection queues › New York
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in New York — page 15
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| South Suffolk Energy Storage Battery storage · South Suffolk Energy Storage |
100 MW | Withdrawn / abandoned |
| Falls Park Energy Storage Battery storage · Falls Park Energy Storage Project, LLC |
100 MW | Withdrawn / abandoned |
| Sweet Valley Solar Solar · Sweet Valley Energy Center, LLC |
100 MW | Withdrawn / abandoned |
| Horseblock Energy Storage Battery storage · ACE Development Company |
100 MW | Withdrawn / abandoned |
| Stoner Trail Storage Battery storage · Granada Solar, LLC |
100 MW | Withdrawn / abandoned |
| Farmersville Windpark Onshore wind · Noble Environmental Power, LLC |
100 MW | Withdrawn / abandoned |
| Gunns Corners Solar Solar + storage · Northland Power U.S. Projects |
100 MW | Withdrawn / abandoned |
| Hickory Hill Energy Storage Battery storage · BGTF US Development Holdings LLC |
100 MW | Withdrawn / abandoned |
| North Catskill Energy Storage Battery storage · BayWa r.e. Development LLC |
100 MW | Withdrawn / abandoned |
| Arch 3 Battery storage · Terra-Gen Development, LLC |
100 MW | Withdrawn / abandoned |
| Dix Hills, LLC Battery storage · Dix Hills Storage LLC |
100 MW | Withdrawn / abandoned |
| Honey Ridge Solar Solar · Honey Ridge Solar 1, LLC |
100 MW | Withdrawn / abandoned |
| Mill Point Solar II Solar + storage · ConnectGen Montgomery County LLC |
100 MW | Withdrawn / abandoned |
| White Creek Solar Solar · White Creek Solar LLC |
100 MW | Withdrawn / abandoned |
| Moffitt ESC Battery storage · Fresh Air Energy II |
100 MW | Withdrawn / abandoned |
| NSF Aurelius BESS, LLC Battery storage · NSF Aurelius BESS |
100 MW | Withdrawn / abandoned |
| Janes Road Energy Storage Battery storage · MN8 Energy Development Company LLC |
100 MW | Withdrawn / abandoned |
| Fort Edward Solar Farm (NY53) Solar · Fort Edward Solar |
100 MW | Withdrawn / abandoned |
| Richardson BESS Battery storage · ACE DevCo NC, LLC |
100 MW | Withdrawn / abandoned |
| Verona Storage Battery storage · Invenergy Solar Development LLC |
100 MW | Withdrawn / abandoned |
| Flat Creek Solar II Solar · Flat Creek Solar NY LLC |
100 MW | Withdrawn / abandoned |
| Moresville Energy Center Onshore wind · Moresville Energy LLC |
99.0 MW | Withdrawn / abandoned |
| Arkwright Windpark Onshore wind · Noble Environmental Power, LLC |
99.0 MW | Withdrawn / abandoned |
| Agricola Wind Onshore wind · Liberty Renewables Inc. |
97.0 MW | Withdrawn / abandoned |
| EI Oceanside Onshore wind · Empire Offshore Wind LLC |
96.0 MW | Withdrawn / abandoned |
| Hell Gate Energy Storage Battery storage · NY Power Authority |
96.0 MW | Withdrawn / abandoned |
| EI Empire ESS I Battery storage · Empire Offshore Wind LLC |
96.0 MW | Withdrawn / abandoned |
| Orangeville Wind Onshore wind · NY Windpower, LLC |
96.0 MW | Withdrawn / abandoned |
| Whale Square Energy Storage 2 Battery storage · Astoria Generating Company, L.P. |
95.7 MW | Withdrawn / abandoned |
| South Pier Improvement Gas · Astoria Generating Co. |
95.5 MW | Withdrawn / abandoned |
| Mustang BESS Battery storage · Viridity Energy Solutions |
95.0 MW | Withdrawn / abandoned |
| Berrians East Replacement Gas · NRG Berrians East Development, LLC |
94.2 MW | Withdrawn / abandoned |
| Moraine Solar Energy Center Solar · EDF Renewables Development, Inc. |
93.6 MW | Withdrawn / abandoned |
| Worth Wind Onshore wind · SWEB Development USA, LLC |
92.0 MW | Withdrawn / abandoned |
| Ogdensburg Gas · AG Energy, LP |
90.1 MW | Withdrawn / abandoned |
| North Seneca Solar · North Seneca Solar Project, LLC |
90.0 MW | Withdrawn / abandoned |
| Hallock Ave Energy Storage Battery storage · Borrego Solar Systems, inc. |
90.0 MW | Withdrawn / abandoned |
| York Run Solar, LLC Solar · York Run Solar, LLC |
90.0 MW | Withdrawn / abandoned |
| Hickling Storage, LLC Battery storage · Hickling Storage, LLC |
90.0 MW | Withdrawn / abandoned |
| Kce NY 22 Battery storage · KCE NY 22, LLC |
90.0 MW | Withdrawn / abandoned |
| Berrians GT II Gas · NRG Energy, Inc. |
90.0 MW | Withdrawn / abandoned |
| Goldenrod Solar Solar · Granada Solar, LLC (Conti) |
90.0 MW | Withdrawn / abandoned |
| Champlain Solar Solar · RWE Clean Energy Development, LLC |
90.0 MW | Withdrawn / abandoned |
| Ball Hill Windpark Onshore wind · Ball Hill Windpark, LLC |
90.0 MW | Withdrawn / abandoned |
| Yellow Feather Solar · Yellow Feather Energy Center, LLC |
90.0 MW | Withdrawn / abandoned |
| Machias Wind Farm Onshore wind · Machias Wind Farm, LLC |
90.0 MW | Withdrawn / abandoned |
| Danskammer Energy Center Gas · Danskammer Energy LLC |
88.9 MW | Withdrawn / abandoned |
| Erie Power Gas · Erie Power, LLC |
88.0 MW | Withdrawn / abandoned |
| Hemlock Hollow Wind Onshore wind · Liberty Renewables Inc. |
87.9 MW | Withdrawn / abandoned |
| Cuba Wind Project Onshore wind · SWEB Development USA, LLC |
86.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)