GAS Β· NYISO

Erie Power

Erie Power is a 88.0 MW gas request withdrawn in the NYISO interconnection queue, in Chautauqua County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2014 (completed)
  2. Withdrawn / abandonedFeb 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
440
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Erie Power, LLC
Connection point (POI)
South Ripley Substation 230kV
Location
Chautauqua County, New York
Technology
Gas: 88.0 MW
Total requested
88.0 MW
Queue status
Withdrawn
Entered queue
2 June 2014
Withdrawn
February 2018

Location

Marker shows the centre of Chautauqua County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Chautauqua County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem