United States › Grid › Interconnection queues › New York

ONSHORE WIND · NYISO

Moresville Energy Center

Moresville Energy Center is a 99.0 MW onshore wind request withdrawn in the NYISO interconnection queue, in Delaware County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2004 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
152
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Moresville Energy LLC
Connection point (POI)
Axtell Road-Grand Gorge 115kV
Location
Delaware County, New York
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Queue status
Withdrawn
Entered queue
23 July 2004
Withdrawn
June 2011

Location

Marker shows the centre of Delaware County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Delaware County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem