United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOFraser Storage
Fraser Storage is a 200 MW battery storage request withdrawn in the NYISO interconnection queue, in Delaware County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1362
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- EDF renewables development inc.
- Connection point (POI)
- Fraser substation 115 kV
- Location
- Delaware County, New York
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Queue status
- Withdrawn
- Entered queue
- 12 April 2022
Location
Marker shows the centre of Delaware County; the queue data does not give exact sites.
Other requests in Delaware County
- Fraser Energy StorageBattery storage · 135 MW · in study
- Stonewall Solar, LLC.Solar · 145 MW · withdrawn
- Stonewall SolarSolar + storage · 145 MW · withdrawn
- Birch-WhistlerOnshore wind · 100 MW · withdrawn
- Moresville Energy CenterOnshore wind · 99.0 MW · withdrawn
- Franklin WindOnshore wind · 50.4 MW · withdrawn
- Turkey Hollow SolarSolar · 20.0 MW · withdrawn
- Harpersfield Bruce Hill Rd.Solar · 19.9 MW · withdrawn
- Stonewall Add-onBattery storage · 19.7 MW · withdrawn
- Bruce Hill WindOnshore wind · 18.0 MW · withdrawn
- South Mountain WindOnshore wind · 18.0 MW · withdrawn
- Delaware County LandfillOther · 1.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem