United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 14

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 14 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Other project Q609, Navajo County
Other
500 MWIn study Navajo, AZWest May 2025target 2026
Solar + storage project Company 256, Nye County
Solar + storage
500 MWIn study Nye, NVWest Sep 2023target 2029
Solar + storage project G0478, Morrow County
Solar + storage
500 MWIn study Morrow, ORWest Sep 2012target 2016
Onshore wind project G0558, Benton County
Onshore wind
500 MWIn study Benton, WAWest Feb 2017target 2019
Onshore wind project G0871, Lake County
Onshore wind
500 MWIn study Lake, ORWest Jun 2023target 2028
Battery storage project G0915, Douglas County
Battery storage
500 MWIn study Douglas, WAWest Jul 2023target 2028
Battery storage project G0656, Grant County
Battery storage
500 MWIn study Grant, WAWest Sep 2020target 2023
Solar project IC-1147, Monroe County
Solar
500 MWPaused / redesign Monroe, GASoutheast Jun 2023target 2030
Aquila Solar
Solar · Ben Milam Solar 5
500 MWIn study Milam, TXERCOT Nov 2025target 2026
Battery storage project G0916, Douglas County
Battery storage
500 MWIn study Douglas, WAWest Jul 2023target 2028
Onshore wind project 5RSC-2024-15, Kiowa County
Onshore wind
500 MWIn study Kiowa, COWest Jan 2024target 2027
Solar project GEN-2020-087, Comanche County
Solar
500 MWIn study Comanche, OKSPP Apr 2020target 2026
Solar + storage project Company OX, Lyon County
Solar + storage
500 MWPaused / redesign Lyon, NVWest Jan 2023target 2028
Solar + storage project J4106, Cass County
Solar + storage
500 MWIn study Cass, NDMISO Oct 2025target 2027
Onshore wind project ERAS-2025-021, Hale County
Onshore wind
500 MWIn study Hale, TXSPP Oct 2025target 2030
Onshore wind project J3860, Peoria County
Onshore wind
500 MWIn study Peoria, ILMISO Jan 2025target 2030
Solar + storage project GEN-2024-304, Roosevelt County
Solar + storage
500 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Betel Storage I
Battery storage · BETEL STORAGE I
500 MWIn study Milam, TXERCOT Jan 2025target 2026
Battery storage project Company QQ, Washoe County
Battery storage
500 MWIn study Washoe, NVWest Mar 2024target 2028
Solar + storage project Q368, Yuma County
Solar + storage
500 MWIn study Yuma, AZWest Mar 2021target 2026
Solar project J2696, Mississippi County
Solar
500 MWIn study Mississippi, ARMISO Sep 2022target 2027
Solar + storage project Company OV, Lyon County
Solar + storage
500 MWPaused / redesign Lyon, NVWest Jan 2023target 2028
Solar + storage project NC5-010, Kane County
Solar + storage
500 MWIn study Kane, UTWest Mar 2024target 2028
Solar + storage project GI-2023-167, Imperial County
Solar + storage
500 MWIn study Imperial, CAWest Feb 2023target 2026
Battery storage project 2024-MP1, Mohave County
Battery storage
500 MWIn study Mohave, AZWest Jan 2024target 2028
Battery storage project IC-1170, Douglas County
Battery storage
500 MWPaused / redesign Douglas, GASoutheast Aug 2023target 2030
Battery storage project J2590, Huron County
Battery storage
500 MWIn study Huron, MIMISO Sep 2022target 2025
Solar project J3532, Roseau County
Solar
500 MWIn study Roseau, MNMISO Apr 2024target 2028
Battery storage project J4194, Meeker County
Battery storage
500 MWIn study Meeker, MNMISO Oct 2025target 2028
Solar + storage project Company PK, Esmeralda County
Solar + storage
500 MWIn study Esmeralda, NVWest Mar 2022target 2027
Solar + storage project J2190, Mississippi County
Solar + storage
500 MWIn study Mississippi, ARMISO Aug 2021target 2027
Betel Storage II
Battery storage · BETEL STORAGE II
500 MWIn study Milam, TXERCOT Jan 2025target 2026
Solar project J1855, Jackson County
Solar
500 MWIn study Jackson, ARMISO Nov 2021target 2026
Solar + storage project Q111, Clark County
Solar + storage
500 MWIn study Clark, NVWest Jun 2024target 2026
Solar + storage project Q67, Clark County
Solar + storage
500 MWIn study Clark, NVWest Mar 2019target 2022
Battery storage project 25-IC-1311, Mcduffie County
Battery storage
500 MWIn study Mcduffie, GASoutheast Apr 2025target 2028
Battery storage project G0863, Sherman County
Battery storage
500 MWIn study Sherman, ORWest May 2023target 2027
Other project J2171, Perry County
Other
500 MWIn study Perry, ILMISO Mar 2022target 2024
Onshore wind project 5RSC-2024-28, Kit Carson County
Onshore wind
500 MWIn study Kit Carson, COWest Jan 2024target 2025
Cider Solar
Solar · Hecate Energy Cider Solar LLC
500 MWIn study Genesee, NYNYISO Apr 2019target 2027
Pepper Hammock 500 Solar
Solar
500 MWIn study Glynn, GASoutheast Jul 2022target 2024
Onshore wind project CSUT-2025-1, Lincoln County
Onshore wind
500 MWIn study Lincoln, COWest Mar 2025target 2027
Solar + storage project Q89, Kern County
Solar + storage
500 MWIn study Kern, CAWest Apr 2022target 2027
Vulcan
Solar + storage
500 MWIn study Maricopa, AZCAISO Apr 2018target 2027
Solar project G1015, Benton County
Solar
500 MWIn study Benton, WAWest Nov 2023target 2029
Solar + storage project 25-00421, Mohave County
Solar + storage
500 MWIn study Mohave, AZWest Jul 2025target 2029
Battery storage project J4100, Livingston Parish County
Battery storage
500 MWIn study Livingston Parish, LAMISO Oct 2025target 2030
Battery storage project Company 251, Clark County
Battery storage
500 MWPaused / redesign Clark, NVWest Mar 2023target 2028
Battery storage project J4082, Jefferson County
Battery storage
500 MWIn study Jefferson, ARMISO Oct 2025target 2030
Onshore wind project J2841, Independence County
Onshore wind
500 MWIn study Independence, ARMISO Sep 2022target 2025
Page 14 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)