United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTAquila Solar
Aquila Solar is a 500 MW solar request in interconnection study in the ERCOT interconnection queue, in Milam County, Texas.
Queue statusIn planning
- PlanningQueued Nov 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0635
- Grid region
- ERCOT (Texas)
- Developer
- Ben Milam Solar 5
- Connection point (POI)
- 3706 Gibson Switch 345kV
- Location
- Milam County, Texas
- Technology
- Solar: 500 MW
- Total requested
- 500 MW
- Study phase
- SS Started, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 18 November 2025
- Proposed online date
- November 2026
Location
Marker shows the centre of Milam County; the queue data does not give exact sites.
Other requests in Milam County
- Sypert Branch Solar ProjectSolar Β· 261 MW Β· agreement signed
- Eastbell Milam SolarSolar Β· 245 MW Β· agreement signed
- Adelite StorageBattery storage Β· 232 MW Β· agreement signed
- Hoyte SolarSolar Β· 207 MW Β· agreement signed
- Stoneridge SolarSolar Β· 202 MW Β· agreement signed
- Yaupon Solar SLFSolar Β· 201 MW Β· agreement signed
- Camino Santiago SolarSolar Β· 196 MW Β· agreement signed
- Dos Rios Energy Storage SLFBattery storage Β· 165 MW Β· agreement signed
- Eastbell Milam Solar IISolar Β· 151 MW Β· agreement signed
- Happy Dog StorageSolar + storage Β· 105 MW Β· agreement signed
- Stoneridge BESSBattery storage Β· 102 MW Β· agreement signed
- HappyDogSolarSolar + storage Β· 85.5 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem