United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2017 requests) — page 13
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project TCS-03, Iron County Solar + storage |
77.5 MW | Withdrawn / abandoned |
| Solar project Q59, Kern County Solar |
77.0 MW | Withdrawn / abandoned |
| Cassiopeia Solar Solar |
77.0 MW | Withdrawn / abandoned |
| Battery storage project GEN-2017-225, Johnson County Battery storage |
76.0 MW | Withdrawn / abandoned |
| Battery storage project GEN-2017-229, Johnson County Battery storage |
76.0 MW | Withdrawn / abandoned |
| Solar project 56, Berkeley County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 909, Tooele County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 70688, Greenwood County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 201, Alachua County Solar · Masked |
75.0 MW | Withdrawn / abandoned |
| Solar project 61, Dillon County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 57, Williamsburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project J892, Walworth County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 58, Barnwell County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 59, Aiken County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 60, Clarendon County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 43, Orangeburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project GI-2017-48, Weld County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 55, Allendale County Solar |
75.0 MW | Withdrawn / abandoned |
| Woodbridge Energy Center Gas |
75.0 MW | Withdrawn / abandoned |
| Solar project GI-2017-51, Arapahoe County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 52, Colleton County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 17236, Lee County Solar · Masked |
75.0 MW | Withdrawn / abandoned |
| Offshore Wind with battery addition Other |
75.0 MW | Withdrawn / abandoned |
| Millhouse Solar Solar · Cypress Creek Renewables |
75.0 MW | Withdrawn / abandoned |
| Solar project 53, Newberry County Solar |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project J887, Knox County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Solar project 189C, Alachua County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project AD2-013, Hertford County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 198, Citrus County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 194B, Hamilton County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 202A, Columbia County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-580, Mitchell County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 177, Highlands County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-579, Irwin County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 205, Levy County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 187, Hernando County Solar · Lockhart Hills Energy LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project AD1-034, Sussex County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-658, Jackson County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-599, Calhoun County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-654, Okaloosa County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 993, Weber County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 175, Highlands County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-581, Wilkes County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 184, Alachua County Solar · Archer Solar Project, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 28, Hillsborough County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 193A, Osceola County Solar · Invenergy Solar Project Development LLC |
74.5 MW | Withdrawn / abandoned |
| Solar project 6, Manatee County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 191, Osceola County Solar · Invenergy Solar Project Development LLC |
74.5 MW | Withdrawn / abandoned |
| Solar project 5, Manatee County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 10, Manatee County Solar |
74.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)302 · 46.9 GW
- SPP (Southwest Power Pool)162 · 32.0 GW
- MISO (Midcontinent)127 · 19.9 GW
- PJM (Mid-Atlantic, Midwest)236 · 18.3 GW
- Southeast (non-ISO utilities)208 · 16.9 GW
- CAISO (California)65 · 11.3 GW
- ERCOT (Texas)55 · 8,908 MW
- ISO-NE (New England)42 · 4,856 MW
- NYISO (New York)61 · 2,565 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)