United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2017 requests) — page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,258161.7 GW
Active in queue51.0 GW292 requests
Agreement signed32.8 GW182 requests
Withdrawn1,258161.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,258 requests · page 13 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project TCS-03, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2023
Solar project Q59, Kern County
Solar
77.0 MWWithdrawn / abandoned Kern, CAWest Mar 2017target 2020
Cassiopeia Solar
Solar
77.0 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2021
Battery storage project GEN-2017-225, Johnson County
Battery storage
76.0 MWWithdrawn / abandoned Johnson, KSSPP Nov 2017target 2026
Battery storage project GEN-2017-229, Johnson County
Battery storage
76.0 MWWithdrawn / abandoned Johnson, KSSPP Nov 2017target 2026
Solar project 56, Berkeley County
Solar
75.0 MWWithdrawn / abandoned Berkeley, SCSoutheast Nov 2017target 2019
Solar project 909, Tooele County
Solar
75.0 MWWithdrawn / abandoned Tooele, UTWest Jul 2017target 2018
Solar project 70688, Greenwood County
Solar
75.0 MWWithdrawn / abandoned Greenwood, SCSoutheast Sep 2017
Solar project 201, Alachua County
Solar · Masked
75.0 MWWithdrawn / abandoned Alachua, FLSoutheast Oct 2017target 2019
Solar project 61, Dillon County
Solar
75.0 MWWithdrawn / abandoned Dillon, SCSoutheast Nov 2017target 2019
Solar project 57, Williamsburg County
Solar
75.0 MWWithdrawn / abandoned Williamsburg, SCSoutheast Nov 2017target 2019
Solar project J892, Walworth County
Solar
75.0 MWWithdrawn / abandoned Walworth, WIMISO Jun 2017target 2019
Solar project 58, Barnwell County
Solar
75.0 MWWithdrawn / abandoned Barnwell, SCSoutheast Nov 2017target 2019
Solar project 59, Aiken County
Solar
75.0 MWWithdrawn / abandoned Aiken, SCSoutheast Nov 2017target 2019
Solar project 60, Clarendon County
Solar
75.0 MWWithdrawn / abandoned Clarendon, SCSoutheast Nov 2017target 2019
Solar project 43, Orangeburg County
Solar
75.0 MWWithdrawn / abandoned Orangeburg, SCSoutheast Apr 2017target 2019
Solar project GI-2017-48, Weld County
Solar
75.0 MWWithdrawn / abandoned Weld, COWest Nov 2017target 2020
Solar project 55, Allendale County
Solar
75.0 MWWithdrawn / abandoned Allendale, SCSoutheast Nov 2017target 2019
Woodbridge Energy Center
Gas
75.0 MWWithdrawn / abandoned Middlesex, NJPJM Sep 2017target 2021
Solar project GI-2017-51, Arapahoe County
Solar
75.0 MWWithdrawn / abandoned Arapahoe, COWest Dec 2017target 2020
Solar project 52, Colleton County
Solar
75.0 MWWithdrawn / abandoned Colleton, SCSoutheast Nov 2017target 2019
Solar project 17236, Lee County
Solar · Masked
75.0 MWWithdrawn / abandoned Lee, SCSoutheast Aug 2017
Offshore Wind with battery addition
Other
75.0 MWWithdrawn / abandoned MAISO-NE Dec 2017target 2023
Millhouse Solar
Solar · Cypress Creek Renewables
75.0 MWWithdrawn / abandoned Jim Wells, TXERCOT Nov 2017target 2020
Solar project 53, Newberry County
Solar
75.0 MWWithdrawn / abandoned Newberry, SCSoutheast Nov 2017target 2019
Onshore wind project J887, Knox County
Onshore wind
75.0 MWWithdrawn / abandoned Knox, ILMISO Jun 2017target 2019
Solar project 189C, Alachua County
Solar · Masked
74.9 MWWithdrawn / abandoned Alachua, FLSoutheast Jun 2017target 2020
Solar project AD2-013, Hertford County
Solar
74.9 MWWithdrawn / abandoned Hertford, NCPJM Nov 2017target 2020
Solar project 198, Citrus County
Solar · Masked
74.9 MWWithdrawn / abandoned Citrus, FLSoutheast Sep 2017target 2020
Solar project 194B, Hamilton County
Solar · Masked
74.9 MWWithdrawn / abandoned Hamilton, FLSoutheast Sep 2017target 2020
Solar project 202A, Columbia County
Solar · Masked
74.9 MWWithdrawn / abandoned Columbia, FLSoutheast Oct 2017target 2019
Solar project IC-580, Mitchell County
Solar
74.9 MWWithdrawn / abandoned Mitchell, GASoutheast Jan 2017
Solar project 177, Highlands County
Solar · Masked
74.9 MWWithdrawn / abandoned Highlands, FLSoutheast Feb 2017target 2020
Solar project IC-579, Irwin County
Solar
74.9 MWWithdrawn / abandoned Irwin, GASoutheast Jan 2017
Solar project 205, Levy County
Solar · Masked
74.9 MWWithdrawn / abandoned Levy, FLSoutheast Nov 2017target 2021
Solar project 187, Hernando County
Solar · Lockhart Hills Energy LLC
74.9 MWWithdrawn / abandoned Hernando, FLSoutheast Jun 2017target 2021
Solar project AD1-034, Sussex County
Solar
74.9 MWWithdrawn / abandoned Sussex, VAPJM Jul 2017target 2020
Solar project IC-658, Jackson County
Solar
74.9 MWWithdrawn / abandoned Jackson, FLSoutheast Dec 2017
Solar project IC-599, Calhoun County
Solar
74.9 MWWithdrawn / abandoned Calhoun, FLSoutheast Feb 2017
Solar project IC-654, Okaloosa County
Solar
74.9 MWWithdrawn / abandoned Okaloosa, FLSoutheast Oct 2017
Solar project 993, Weber County
Solar
74.9 MWWithdrawn / abandoned Weber, UTWest Dec 2017target 2020
Solar project 175, Highlands County
Solar · Masked
74.9 MWWithdrawn / abandoned Highlands, FLSoutheast Jan 2017target 2020
Solar project IC-581, Wilkes County
Solar
74.9 MWWithdrawn / abandoned Wilkes, GASoutheast Jan 2017
Solar project 184, Alachua County
Solar · Archer Solar Project, LLC
74.9 MWWithdrawn / abandoned Alachua, FLSoutheast May 2017target 2021
Solar project 28, Hillsborough County
Solar
74.5 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2017target 2018
Solar project 193A, Osceola County
Solar · Invenergy Solar Project Development LLC
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Aug 2017target 2022
Solar project 6, Manatee County
Solar
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Apr 2017target 2020
Solar project 191, Osceola County
Solar · Invenergy Solar Project Development LLC
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Jul 2017target 2022
Solar project 5, Manatee County
Solar
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Apr 2017target 2020
Solar project 10, Manatee County
Solar
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Apr 2017target 2020
Page 13 of 26

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)