United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

SOLAR Β· SOUTHEAST

Solar project IC-654, Okaloosa County

Solar project IC-654, Okaloosa County is a 74.9 MW solar request withdrawn in the Southeast interconnection queue, in Okaloosa County, Florida, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2017 (completed)
  2. Withdrawn / abandonedFeb 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-654
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Crist - South Crestview #1 115 kV Line
Location
Okaloosa County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
31 October 2017
Withdrawn
February 2019

Location

Marker shows the centre of Okaloosa County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Okaloosa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem