Solar project 366D, Okaloosa County

Solar project 366D, Okaloosa County is a 74.9 MW solar request withdrawn in the Southeast interconnection queue, in Okaloosa County, Florida, connecting to Florida Power & Light.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
366D
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
Third Party
Connection point (POI)
Shoal River - Samson (APC) 230 kV line
Location
Okaloosa County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Withdrawn
Entered queue
18 April 2019
Proposed online date
October 2029

Location

Marker shows the centre of Okaloosa County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Okaloosa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem