πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Carolina

SOLAR Β· SOUTHEAST

Solar project 55, Allendale County

Solar project 55, Allendale County is a 75.0 MW solar request withdrawn in the Southeast interconnection queue, in Allendale County, South Carolina, connecting to Santee Cooper.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
55
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Santee Cooper
Location
Allendale County, South Carolina
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
16 November 2017
Proposed online date
December 2019

Location

Marker shows the centre of Allendale County; the queue data does not give exact sites.

Power plants in South Carolina Β· Transmission lines in South Carolina

Other requests in Allendale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem