SOLAR + STORAGE Β· SOUTHEASTSolar + storage project 20230829010, Allendale County
Solar + storage project 20230829010, Allendale County is a 50.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Allendale County, South Carolina, connecting to Dominion Energy South Carolina.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20230829010
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Dominion Energy South Carolina
- Connection point (POI)
- Fairfax βΓΓ¬ Yemassee 115 kV
- Location
- Allendale County, South Carolina
- Technology
- Solar: 50.0 MW Β· Battery
- Total requested
- 50.0 MW
- Queue status
- Withdrawn
- Proposed online date
- June 2027
Location
Marker shows the centre of Allendale County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Allendale County
- Other project 32, Allendale CountyOther Β· 19.9 MW Β· built
- Solar project 155, Allendale CountySolar Β· 86.0 MW Β· withdrawn
- Solar project 20171027001, Allendale CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 55, Allendale CountySolar Β· 75.0 MW Β· withdrawn
- Solar + storage project 279, Allendale CountySolar + storage Β· 65.0 MW Β· withdrawn
- Solar project 259, Allendale CountySolar Β· 48.0 MW Β· withdrawn