Offshore Wind with battery addition

Offshore Wind with battery addition is a 75.0 MW other request withdrawn in the ISO-NE interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2017 (completed)
  2. Withdrawn / abandonedFeb 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
699
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid 345 kV Brayton Point Substation, Somerset, MA
Location
Massachusetts
Technology
Offshore Wind: 75.0 MW Β· Battery
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
13 December 2017
Proposed online date
May 2023
Withdrawn
February 2019

Location

No county location in the queue data.