United States βΊ Grid βΊ Interconnection queues βΊ Massachusetts
OTHER Β· ISO-NEOffshore Wind with battery addition
Offshore Wind with battery addition is a 75.0 MW other request withdrawn in the ISO-NE interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2017 (completed)
- Withdrawn / abandonedFeb 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 699
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- National Grid 345 kV Brayton Point Substation, Somerset, MA
- Location
- Massachusetts
- Technology
- Offshore Wind: 75.0 MW Β· Battery
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 13 December 2017
- Proposed online date
- May 2023
- Withdrawn
- February 2019
Location
No county location in the queue data.
Power plants in Massachusetts Β· Transmission lines in Massachusetts