Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 10 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 136, Converse County
Onshore wind · Clipper Windpower Development Company, Inc
500 MWWithdrawn / abandoned Converse, WYWest May 2007target 2012
Battery storage project 153, Pima County
Battery storage
500 MWWithdrawn / abandoned Pima, AZWest Mar 2023target 2028
Onshore wind project 872, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest May 2017target 2020
Solar + storage project Company PS, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Mar 2023target 2027
Onshore wind project GI-2010-21, Kit Carson County
Onshore wind
500 MWWithdrawn / abandoned Kit Carson, COWest Dec 2010target 2014
Coal project GI-2003-2, Elbert County
Coal
500 MWWithdrawn / abandoned Elbert, COWest Nov 2003target 2008
Battery storage project C2-23, Converse County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest Apr 2022target 2028
Battery storage project SP114, Navajo County
Battery storage
500 MWWithdrawn / abandoned Navajo, AZWest target 2026
Solar + storage project Company PX, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Mar 2023target 2028
Solar + storage project 671, Lincoln County
Solar + storage
500 MWWithdrawn / abandoned Lincoln, IDWest Oct 2022
Onshore wind project G0876, Klickitat County
Onshore wind
500 MWWithdrawn / abandoned Klickitat, WAWest Jun 2023target 2029
Battery storage project C3-064, Sanpete County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Sanpete, UTWest May 2023target 2030
Battery storage project Q452, Maricopa County
Battery storage
500 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2025
Solar project GI-2017-46, Huerfano County
Solar
500 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Solar project GI-2021-30, Morgan County
Solar
500 MWWithdrawn / abandoned Morgan, COWest Oct 2021target 2024
Solar + storage project Company OR, Lander County
Solar + storage
500 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2035
Solar project Q70, Coconino County
Solar
500 MWWithdrawn / abandoned Coconino, AZWest Jul 2009target 2012
Solar + storage project Q351, Navajo County
Solar + storage
500 MWWithdrawn / abandoned Navajo, AZWest Sep 2020target 2024
Battery storage project C3-066, Converse County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest May 2023target 2030
Onshore wind project PIS004, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest Apr 2022target 2025
Solar + storage project Company QY, Churchill County
Solar + storage
500 MWWithdrawn / abandoned Churchill, NVWest Mar 2024target 2028
Battery storage project C2-22, Emery County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Emery, UTWest Apr 2022target 2028
Battery storage project 159, Pinal County
Battery storage
500 MWWithdrawn / abandoned Pinal, AZWest Aug 2023target 2030
Solar + storage project 171, Pinal County
Solar + storage
500 MWWithdrawn / abandoned Pinal, AZWest Jun 2024target 2028
Battery storage project Q510, Yuma County
Battery storage
500 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2028
500MW St Johns-Ross
Gas · Calpine Energy Services, L.P.
500 MWWithdrawn / abandoned Clark, WAWest Feb 2001target 2005
Solar + storage project Q364, Coconino County
Solar + storage
500 MWWithdrawn / abandoned Coconino, AZWest Sep 2020target 2024
Solar + storage project Company OM, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2028
Solar project Q42, Maricopa County
Solar
500 MWWithdrawn / abandoned Maricopa, AZWest Feb 2008target 2013
Solar project GI-2017-11, Lincoln County
Solar
500 MWWithdrawn / abandoned Lincoln, COWest Mar 2017target 2020
Coal project GI-0325, Custer County
Coal
500 MWWithdrawn / abandoned Custer, MTWest Oct 2003
Solar + storage project Q416, Pinal County
Solar + storage
500 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2024
Onshore wind project GI-2008-19, Prowers County
Onshore wind
500 MWWithdrawn / abandoned Prowers, COWest Sep 2008target 2011
Onshore wind project Q26, Mohave County
Onshore wind
500 MWWithdrawn / abandoned Mohave, AZWest Sep 2006target 2009
Gas project Q257, Pinal County
Gas
500 MWWithdrawn / abandoned Pinal, AZWest Jun 2017target 2021
Gas project 10, Klamath County
Gas · Iberdrola Renewables, Inc.
500 MWWithdrawn / abandoned Klamath, ORWest Apr 2001target 2005
Battery storage project C3-065, Emery County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Emery, UTWest May 2023target 2030
Solar + storage project Company KB, Washoe County
Solar + storage
500 MWWithdrawn / abandoned Washoe, NVWest Sep 2019target 2022
Solar + storage project 161, Cochise County
Solar + storage
500 MWWithdrawn / abandoned Cochise, AZWest Sep 2023target 2030
Other project Q533, Coconino County
Other
500 MWWithdrawn / abandoned Coconino, AZWest Apr 2023target 2027
Coal project 20, Rosebud County
Coal
500 MWWithdrawn / abandoned Rosebud, MTWest Mar 2002target 2013
Solar project 560, Elmore County
Solar
500 MWWithdrawn / abandoned Elmore, IDWest Jun 2019
Solar + storage project Company MF, Humboldt County
Solar + storage
500 MWWithdrawn / abandoned Humboldt, NVWest Sep 2021target 2024
Battery storage project Company PJ, Humboldt County
Battery storage
500 MWWithdrawn / abandoned Humboldt, NVWest Mar 2022target 2029
Battery storage project Company PV, Eureka County
Battery storage
500 MWWithdrawn / abandoned Eureka, NVWest Mar 2023target 2028
Onshore wind project C3-016, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2023target 2025
Onshore wind project 191, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest Jan 2008
Solar + storage project 114, Pima County
Solar + storage
500 MWWithdrawn / abandoned Pima, AZWest Feb 2022target 2026
Battery storage project C3-152, Sevier County
Battery storage
500 MWWithdrawn / abandoned Sevier, UTWest May 2023target 2027
Battery storage project C2-21, Juab County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Juab, UTWest Apr 2022target 2028
Page 10 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)