Parc Cynog
Parc Cynog is a 3.6 MW onshore wind farm in Wales, operated by European Energy A/S. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- Wales
Key facts
- Installed capacity
- 3.6 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- European Energy A/S
- Region
- Wales
- Country
- Wales
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SA33 4PY
- Coordinates
- 51.7569, -4.5297
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Parc Cynog compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 3.6 MW station would generate roughly 8.2 GWh of electricity in a year, similar to the annual use of about 3,040 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in Wales All run by European Energy A/SNearby generating sites
- Pendine Wind Farm Limited Β· 4.8 MW onshore wind farm0.4 km
- PV@Pendine Solar Farm Β· 4.9 MW solar farm1.5 km
- Dyffryn Brodyn Wind Farm (GB) Β· 5.4 MW onshore wind farm17.6 km
- Ffos Las Β· 5 MW solar farm20.4 km
- Jordanston Solar Farm Β· 4.63 MW solar farm20.5 km
- Oak Cottage Β· 4.87 MW solar farm24.1 km
- Brynteg Β· 14.8 MW solar farm24.7 km
- West Farm Β· 7.63 MW solar farm26.4 km
Also operated by European Energy A/S
European Energy A/S operates 10 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Parc-Cynog Wind Farm
- Developer / operator
- Micon Wind Turbines (UK) Limited
- Planning authority
- Carmarthenshire
- Application submitted
- 5 May 1998
- Permission granted
- 1 February 2000
- Began operating
- 1 February 2001
- Capacity in planning record
- 3.6 MW
- Address
- Parc-Cynog Farm Pendine Carmarthenshire, Dyfed
- REPD reference
- 2636
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026