πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
WIND Β· OPERATIONAL

Greendykeside

Greendykeside is a 4 MW onshore wind farm in Scotland, operated by Temporis Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland
Project stageOperating
  1. PlanningSep 2004 (completed)
  2. ConsentedMay 2005 (completed)
  3. Construction (completed)
  4. OperatingNov 2007 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Temporis Capital
Region
Scotland
Country
Scotland
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
ML6 7TT
Coordinates
55.9120, -3.9032

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Greendykeside compares

433rd of 488largest wind farms in the UK register
192nd of 199in Scotland
0.01%of listed UK wind farms capacity
β‰ˆ 9.1 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 4 MW station would generate roughly 9.1 GWh of electricity in a year, similar to the annual use of about 3,370 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Temporis Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
A7 Energy
Planning authority
North Lanarkshire
Planning reference
04/01624/FUL
Application submitted
13 September 2004
Permission granted
11 May 2005
Began operating
1 November 2007
Capacity in planning record
4 MW
Address
Greendykeside Farm , Longriggend , Airdrie , Lanarkshire, Strathclyde, ML6 7TT
REPD reference
3236

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.