WIND Β· OPERATIONAL

Burnhead Moss

Burnhead Moss is a 26 MW onshore wind farm in Scotland, operated by EDF Energy. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland
Project stageOperating
  1. PlanningDec 2010 (completed)
  2. ConsentedOct 2013 (completed)
  3. ConstructionJan 2015 (completed)
  4. OperatingFeb 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
26 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
EDF Energy
Region
Scotland
Country
Scotland
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
FK1 2JW
Coordinates
55.9272, -3.7860

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Burnhead Moss compares

186th of 488largest wind farms in the UK register
116th of 199in Scotland
0.09%of listed UK wind farms capacity
β‰ˆ 59 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 26 MW station would generate roughly 59 GWh of electricity in a year, similar to the annual use of about 21,930 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by EDF Energy

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Burnhead
Developer / operator
Wind Prospect Developments/ EDF
Planning authority
Falkirk
Planning reference
P/10/0857/FUL
Application submitted
17 December 2010
Permission granted
8 October 2013
Construction started
10 January 2015
Began operating
29 February 2016
Capacity in planning record
26 MW
Address
S/Of Stoneridge, Falkirk,, Stirling
REPD reference
4125

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026